Agency Milestone Date of 09/08/2023 for Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) has passed by 1 business days
Milestones:
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21, 2023. Awaiting execution of Sec 106 MOA prior to issuance of ROD.
-
Monthly Status Report for October 2023:On track to meet the alternative completion date of Nov 21, 2023
-
Non-conformance Explanation:BOEM’s FEIS must incorporate measures resulting from Sec 7 consultations. The prior milestone date for publication of the FEIS was Sep 8. NMFS concluded ESA consultation on Sep 8 with issuance of the Biological Opinion, with reasonable and prudent measures (RPMs), terms and conditions, and conservation recommendations. BOEM needed an additional week to analyze and incorporate the NMFS recommendations into the FEIS. BOEM published the FEIS on Sep 15.
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21, 2023. Awaiting execution of Sec 106 MOA prior to issuance of ROD.
-
Monthly Status Report for October 2023:On track to meet the alternative completion date of Nov 21, 2023
-
Non-conformance Explanation:BOEM’s FEIS must incorporate measures resulting from Sec 7 consultations. The prior milestone date for publication of the FEIS was Sep 8. NMFS concluded ESA consultation on Sep 8 with issuance of the Biological Opinion, with reasonable and prudent measures (RPMs), terms and conditions, and conservation recommendations. BOEM needed an additional week to analyze and incorporate the NMFS recommendations into the FEIS. BOEM published the FEIS on Sep 15.
PROJECT WEBSITE: Equinor's Empire Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/11/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
Equinor Wind proposes to construct and operate the Empire Wind Energy Project located in Lease Area OCS-A 0512, which covers approximately 79,350 acres (ac; 32,112 hectares [ha]) and is located approximately 14 statute miles (mi) (12 nautical miles [nm], 22 kilometers [km]) south of Long Island, New York and 19.5 mi (16.9 nm, 31.4 km) east of Long Branch, New Jersey. The project includes development of the lease area in two wind farms, known as Empire Wind 1 (EW 1) and Empire Wind 2 (EW 2). EW 1 and EW 2 will be electrically isolated and independent from each other. Empire Wind proposes to construct and operate up to 147 wind turbines and up to 2 offshore substations with 2 cable routes under the terms of the Renewable Energy Lease.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the EIS, COP, Section 106, ESA, EFH, Section 10/404 completion date on March 23, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the OCS Air Permit completion date on September 06, 2023. The Executive Director determination is posted here.
<style type="text/css"><!--td {border: 1px solid #cccccc;}br {mso-data-placement:same-cell;}-->
</style>
On track to meet the alternative completion date of Nov 21, 2023. Awaiting execution of Sec 106 MOA prior to issuance of ROD.</p>
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21, 2023. Awaiting execution of Sec 106 MOA prior to issuance of ROD.
-
Monthly Status Report for October 2023:On track to meet the alternative completion date of Nov 21, 2023
-
Non-conformance Explanation:BOEM’s FEIS must incorporate measures resulting from Sec 7 consultations. The prior milestone date for publication of the FEIS was Sep 8. NMFS concluded ESA consultation on Sep 8 with issuance of the Biological Opinion, with reasonable and prudent measures (RPMs), terms and conditions, and conservation recommendations. BOEM needed an additional week to analyze and incorporate the NMFS recommendations into the FEIS. BOEM published the FEIS on Sep 15.