Rejected
Milestone Extension: Right-of-Way Authorization (DOI-BLM)
Project bonding is needed to issue the notice to proceed. BLM contacted the project sponsor and was not able to get a timeframe in which bonding is expected to be completed. BLM is moving the milestone 6 months to account for the unknown timeframe the sponsor will need to bond the project. This was discussed with FPISC staff on 1/14/22.
Milestone Extension: Authorization and Certification
The only remaining Federal action for this project is BSEE "authorization and certification," which cannot occur until the project sponsor submits, and
Milestone Extension: Authorization and Certification
On 9-21-2021, Hilcorp requested a suspension of operations from BSEE. Their request is under review. If granted, a SOP could be from 2 years or possibly up to 5 years. Also, Hilcorp has not yet submitted the required Oil Spill Response Plan (OSRP). OSRP that meets
FAST-41 Missed Date: Environmental Assessment (EA)
Triggered missed date from extending EA Process Concluded within 30 days of its current target date which was 11/19/2021 and extended to 11/26/2021
FAST-41 Missed Date: Marine Mammal Protection Act (MMPA) Incidental Take Authorization (DOC – NOAA/NMFS)
Triggered missed date from extending Incidental Take Authorization Decision Rendered within 30 days of its current target date which was 10/30/2021 and extended to 12/22/2021