Rejected
Milestone Extension: Authorization and Certification
The only remaining Federal action for this project is BSEE "authorization and certification," which cannot occur until the project sponsor submits, and
Milestone Extension: Authorization and Certification
On 9-21-2021, Hilcorp requested a suspension of operations from BSEE. Their request is under review. If granted, a SOP could be from 2 years or possibly up to 5 years. Also, Hilcorp has not yet submitted the required Oil Spill Response Plan (OSRP). OSRP that meets
FAST-41 Missed Date: Environmental Assessment (EA)
Triggered missed date from extending EA Process Concluded within 30 days of its current target date which was 11/19/2021 and extended to 11/26/2021
FAST-41 Missed Date: Marine Mammal Protection Act (MMPA) Incidental Take Authorization (DOC – NOAA/NMFS)
Triggered missed date from extending Incidental Take Authorization Decision Rendered within 30 days of its current target date which was 10/30/2021 and extended to 12/22/2021
Milestone Extension: Environmental Impact Statement (EIS)
Initial entry was input prior to development of the permitting dashboard. At time of initial entry BOEM was exploring request from Sunrise Wind to expedite the EIS schedule to provide early access to lease area. Following discussions with Cooperating agencies, Sunrise Wind's request could not be accommodated.