Rejected
Milestone Extension: Section 404 Clean Water Act
The revised target date conforms to the revised EIS schedule obtained from BLM.
Milestone Extension: Right-of-Way Authorization (DOI-BLM)
Project bonding is needed to issue the notice to proceed. BLM contacted the project sponsor and was not able to get a timeframe in which bonding is expected to be completed. BLM is moving the milestone 6 months to account for the unknown timeframe the sponsor will need to bond the project. This was discussed with FPISC staff on 1/14/22.
Milestone Extension: Authorization and Certification
The only remaining Federal action for this project is BSEE "authorization and certification," which cannot occur until the project sponsor submits, and