Rejected
Milestone Extension: Environmental Impact Statement (EIS)
BLM received approval to proceed with publishing the FEIS on September 18, 2019 and the new protest resolution policy allows up to 50 days to resolve possible protests instead of 30 days.
FAST-41 Missed Date: Endangered Species Act Consultation (DOI-FWS)
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 04/17/2021 and extended to 05/10/2021
Milestone Extension: Environmental Impact Statement (EIS)
project sponsor factors. project sponsor and cooperating agencies are aware of the date changes
Milestone Extension: Section 106 Review
State Government factors. The project sponsor and cooperating agencies are aware of the date changes