Rejected
FAST-41 Missed Date: Endangered Species Act Consultation (DOI-FWS)
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 04/17/2021 and extended to 05/10/2021
Milestone Extension: Environmental Impact Statement (EIS)
project sponsor factors. project sponsor and cooperating agencies are aware of the date changes
Milestone Extension: Section 106 Review
State Government factors. The project sponsor and cooperating agencies are aware of the date changes
Milestone Extension: Section 106 Review
We did not receive SHPO Concurrence on Eligibility and Effect Determinations until December 17 which has resulted in more time needed to complete the MOA with the various signatories and partners for the project.
FAST-41 Missed Date: Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
Final Required Milestone Date of 03/03/2021 for NOAA Issues any EFH conservation recommendations has passed by 5 business days
FAST-41 Missed Date: Endangered Species Act Consultation (NOAA-NMFS)
Final Required Milestone Date of 03/03/2021 for Conclusion of ESA Consultation has passed by 5 business days