FWS is updating the target completion date of its Fish and Wildlife Coordination Act review to align with the revised EIS completion date. This change will not affect any other aspects of the permitting timetable.
PROJECT WEBSITE: Mid-Barataria Sediment Diversion EIS
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/19/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Water Resources
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Description:
CURRENT STATUS:
The project status for MBSD is now "In Progress"
PROJECT DESCRIPTION:
On June 22, 2016, CPRA submitted a joint permit application which included a brief project description:
"The Mid-Barataria Sediment Diversion is a large scale, complex civil works and ecosystem restoration project. When operated, up to 75,000 cubic feet per second (cfs) of sediment laden water would be diverted from the Mississippi River to the mid-Barataria Basin to reconnect and re-establish the natural or deltaic sediment deposition process between the Mississippi River and the Barataria Basin to deliver sediment, freshwater, and nutrients to reduce land loss and sustain wetlands."
The proposed MBSD project has the potential for significant impacts and requires an Environmental Impact Statement (EIS) under the National Envrionmental Policy Act (NEPA) to inform a permit decision relative to the lead federal agency under Section 404 of the Clean Water Act (Section 404) and Section 10 of the Rivers and Harbors Act (Section 10), and permissions under Section 14 of the Rivers and Harbors Act (Section 408) The USACE-MVN Regulatory permit processing number is MVN-2012-2806-E00.
Additional project details can be found here:
Link to MBSD Regulatory webpage: here
Link to the MBSD Scoping Report (Jan 2018): here
Link to the 11 September 2017 Federal MOU for the MBSD permitting process: here
Link to the 25 January 2018 executed MOU between the State of Louisiana and FAST 41 Cooperating Agencies for the MBSD permit application: here
This Permitting Dashboard includes limitations on the types of milestones that are currently available to enter for tracking. The MBSD project involves some authorizations/laws unsupported by the Permitting Table displayed at the bottom of this webpage. For improved transparency, USACE is providing this supplemental table to track additional authorizations/laws that may be necessary for completion of the regulatory process:
Agency | Action | Milestone Detail | Details/Status | Milestone Date |
---|---|---|---|---|
CPRA | Bipartisan Budget Act of 2018 | CPRA begins consultation with NMFS on marine mammal impact minimizing, monitoring, and evaluation. |
Following issuance of the MMPA waiver, the State will begin consultation with NMFS (using existing coordination processes to the extent possible) regarding practicable measures to minimize impacts to marine mammals, and measures to monitor and evaluate the impacts of the MBSD from construction, operation and maintenance. To date, the project sponsor has been in contact with NMFS about Phase I and Phase II marine mammal baseline data/monitoring. |
End Date not provided by CPRA |
LDOTD | Permit | Temporary access, alter, or use an existing ROW |
Reviewed at the LDOTD district level. Typical timeframe for review of COMPLETE application is 45 days. |
see Details/Status |
LDOTD | Permit | Impacts to construction affecting Louisiana Hwy 23 and for related work within LDOTD ROW |
Reviewed at the LDOTD District and HQ levels. Typical timeframe for review of a COMPLETE application is 90 days. |
see Details/Status |
LDEQ | Certification | Section 401 Water Quality Certification | Needed prior to issuance of a 10/404 permit decision | See Details/Status |
LDNR | CUP | Coastal Use Permit | Currently On-Hold for federal NEPA process; Needed prior to issuance of a 10/404 permit decision | see Details/Status |
Milestone: Issuance of decision for permit/approval
Requested extensions greater than 30 days for this Action are shown below:
Issuance of decision for permit/approval by 143 days
From: 06/26/2020
To: 11/16/2020