Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-05-2021 08-05-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 08-05-2021 08-05-2021 --- Yes
Section 106 consultation concluded (Agency Action) 08-21-2023 12-04-2023 03-22-2024 Yes
In Progress
Section 106 consultation was delayed due to late submission of an updated COP that incorporated new information, including onshore construction activities the Sponsor had initiated.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-05-2021 08-05-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 08-05-2021 08-05-2021 --- Yes
Section 106 consultation concluded (Agency Action) 08-21-2023 12-04-2023 03-21-2024 No
In Progress
In addition to interagency delays in developing project alternatives in June 2022, the project sponsor presented new project information in February 2023, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 22 WTGs for the project due to glauconite sands present within the Lease Area. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations.  This action is dependent upon completion of the ROD.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-05-2021 08-05-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 08-05-2021 08-05-2021 --- Yes
Section 106 consultation concluded (Agency Action) 08-21-2023 12-04-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-05-2021 08-05-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 08-05-2021 08-05-2021 --- Yes
Section 106 consultation concluded (Agency Action) 08-21-2023 08-21-2023 --- No