Permitting Action Modification History

Complete
ahead of schedule. [Completed May 20, a month ahead of posted milestone date of June 21, 2024] , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-05-2022 08-05-2022 --- Yes
Completeness Determination (Agency Action) 09-05-2022 09-05-2022 --- Yes
Complete application submitted (Applicant Action) 11-01-2022 07-14-2023 --- Yes
Issuance of Decision (Agency Action) 11-15-2023 05-20-2024 --- Yes
In Progress
The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10), and installation of splice vaults and duct banks, and the expansion of an existing substation (Phase 1B activities, scheduled to commence around September). BOEM notified Tribal Nations, cooperating agencies, Section 106 consulting parties, and the project sponsor that BOEM did not have authority over these activities and that onshore construction would be moving forward.  While BOEM does not have authority over these onshore activities, BOEM has a responsibility to analyze impacts from all the proposed onshore activities included within the scope of a project as connected actions under the National Environmental Policy Act (NEPA) and Section 106 of the National Historic Preservation Act (NHPA). A Construction and Operations Plan (COP) update was required to move forward with these analyses because the prior COP dated August 18, 2022, did not include enough detailed information regarding the onshore activities. The project sponsor submitted an updated COP to BOEM on September 29, 2023. The updated information was necessary for determining the timeline for concluding the Section 106 process and Record of Decision.  Movement of the ROD is therefore causing movement of this dependent action. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-05-2022 08-05-2022 --- Yes
Completeness Determination (Agency Action) 09-05-2022 09-05-2022 --- Yes
Complete application submitted (Applicant Action) 11-01-2022 07-14-2023 --- Yes
Issuance of Decision (Agency Action) 11-15-2023 06-21-2024 --- No
In Progress
Complete application evaluation was completed earlier than scheduled on the dashboard.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-05-2022 08-05-2022 --- Yes
Completeness Determination (Agency Action) 09-05-2022 09-05-2022 --- Yes
Complete application submitted (Applicant Action) 11-01-2022 07-14-2023 --- Yes
Issuance of Decision (Agency Action) 11-15-2023 03-04-2024 --- No
In Progress
Issuance of Decision milestone change: BOEM presented a 3rd revised schedule to the cooperating agencies on 4/20/23, which included  delays to the DEIS and ROD due to feasibility issues with turbine generator foundations and subsequent updates to consultation and ROD milestones.    The issuance of decision for the Section 408 permission was adjusted accordingly (90 days post-ROD). BOEM to work on Executive Director approval for all schedule changes.  Complete application submitted milestone change:  The USACE determined on 5 Sept 2022 that the applicant did not provide a complete Section 408 application. The applicant submitted additional materials on 4 May 2023, however, additional information is still required. Milestone pushed to 31 July 2023 to provide time for the applicant to submit additional materials and for the USACE to evaluate the adequacy of the materials.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-05-2022 08-05-2022 --- Yes
Completeness Determination (Agency Action) 09-05-2022 09-05-2022 --- Yes
Complete application submitted (Applicant Action) 11-01-2022 07-31-2023 --- No
Issuance of Decision (Agency Action) 11-15-2023 03-04-2024 --- No
In Progress
Applicant was unable to provide documentation by 1 Nov 2022 for a Section 408 complete application. A new estimated timeframe for document submittal and USACE confirmation of a complete package was updated to 14 Dec 2022.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-05-2022 08-05-2022 --- Yes
Completeness Determination (Agency Action) 09-05-2022 09-05-2022 --- Yes
Complete application submitted (Applicant Action) 11-01-2022 12-14-2022 --- No
Issuance of Decision (Agency Action) 11-15-2023 11-15-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-05-2022 08-05-2022 --- Yes
Completeness Determination (Agency Action) 09-05-2022 09-05-2022 --- Yes
Complete application submitted (Applicant Action) 11-01-2022 11-01-2022 --- No
Issuance of Decision (Agency Action) 11-15-2023 11-15-2023 --- No
In Progress
Initial milestone complete 8/5/22 , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-05-2022 08-05-2022 --- Yes
Complete application submitted (Applicant Action) --- --- --- No
Completeness Determination (Agency Action) 09-05-2022 09-05-2022 --- No
Issuance of Decision (Agency Action) 11-15-2023 11-15-2023 --- No