USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Section 106 Review: Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 01/31/2025 for Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
Planned
POC Name:
Robert Nash
POC Title:
Archaeologist
POC Email:
SHPO:

Nevada

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Current Target Date:
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Current Target Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/02/2027

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

Pantheon Solar, LLC proposes to construct, operate, maintain, and eventually decommission a 400-megawatt (MW) solar photovoltaic facility on public lands administered by the U.S. Bureau of Land Management (BLM).  The Project’s primary goal is to produce 400-MW of energy annually, which equates to the annual daytime energy needs of approximately 230,000 households.  The Project site would encompass approximately 2,682 acres of BLM-administered land located approximately 16 miles west of Ely, Nevada.  The Project will include a 500-kilovolt generation tie-line, approximately 6.2 miles in length. Interconnection with the power grid would occur at the Robinson Summit Substation, four miles to the north of the Project site. 

field_status
System Comments
Agency Milestone Date of 01/31/2025 for Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) has passed by 1 business days
Approver Comments
Agency met milestone
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Current Target Date:
Response Date
Reporting Agency