Pantheon Solar Project
PERMITTING DASHBOARD PROJECT POSTING DATE: OCTOBER 18, 2024All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/09/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Description:
Pantheon Solar, LLC proposes to construct, operate, maintain, and eventually decommission a 400-megawatt (MW) solar photovoltaic facility on public lands administered by the U.S. Bureau of Land Management (BLM). The Project’s primary goal is to produce 400-MW of energy annually, which equates to the annual daytime energy needs of approximately 230,000 households. The Project site would encompass approximately 2,682 acres of BLM-administered land located approximately 16 miles west of Ely, Nevada. The Project will include a 500-kilovolt generation tie-line, approximately 6.2 miles in length. Interconnection with the power grid would occur at the Robinson Summit Substation, four miles to the north of the Project site.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|