Agency Milestone Date of 05/02/2026 for Scoping (Agency Action) has passed by 1 business days
Milestones:
-
Monthly Status Report for June 2026:The Bureau of Land Management (BLM) missed the May 2, 2026 milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS) and Resource Management Plan (RMP) Amendment. Per the Department of the Interior National Environmental Policy Act implementation handbook, the BLM is required to publish a Notice of Intent to prepare an EIS when BLM determines an EIS is the appropriate level of NEPA documentation necessary for a proposed project (516 DM 1 Section 1.8 (b)). The Notice of Intent for the Mosey Solar Project is completing necessary agency review and briefings and would be published once those are completed. Per 42 U.S.C.§ 4370m-2(c)(2)(F), BLM is required to provide an alternative completion date and an initial explanation for the missed completion date. BLM has provided the initial explanation for the missed date and is providing June 26, 2026 as an alternative completion date and corrects scoping date to July 26, 2026.
-
Non-conformance Explanation:The Bureau of Land Management (BLM) missed the May 2, 2026 milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS) and Resource Management Plan (RMP) Amendment.Per the Department of the Interior National Environmental Policy Act implementation handbook, the BLM is required to publish a Notice of Intent to prepare an EIS when BLM determines an EIS is the appropriate level of NEPA documentation necessary for a proposed project (516 DM 1 Section 1.8 (b)). The Notice of Intent for the Mosey Solar Project is completing necessary agency review and briefings and would be published once those are completed. Per 42 U.S.C.§ 4370m-2(c)(2)(F), BLM is required to provide an alternative completion date and an initial explanation for the missed completion date. BLM has provided the initial explanation for the missed date and is providing June 26, 2026 as an alternative completion date and corrects scoping date to July 26, 2026.
-
Monthly Status Report for June 2026:The Bureau of Land Management (BLM) missed the May 2, 2026 milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS) and Resource Management Plan (RMP) Amendment. Scoping begins when the NOI is published.
-
Non-conformance Explanation:The Bureau of Land Management (BLM) missed the May 2, 2026 milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS) and Resource Management Plan (RMP) Amendment. Scoping begins when the Notice of Intent is published.
-
Monthly Status Report for June 2026:The Bureau of Land Management (BLM) missed the May 2, 2026 milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS) and Resource Management Plan (RMP) Amendment. Scoping begins when the NOI is published.
-
Non-conformance Explanation:The Bureau of Land Management (BLM) missed the May 2, 2026 milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS) and Resource Management Plan (RMP) Amendment. Scoping begins when the Notice of Intent is published.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/18/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
Clearway Energy Group LLC proposes to construct a 500-megawatt (MW) solar photovoltaic (PV) power generating facility and battery storage facility with up to 850 MW of battery energy storage. The Project would be sited entirely on approximately 3,568 acres of public land administered by the U.S. Bureau of Land Management (BLM) in Pahrump Valley, Nevada. The Project would interconnect to the existing Trout Canyon Substation located approximately 3 miles from the Mosey Solar project area.
The Executive Director granted, in part, and denied, in part, a Bureau of Land Management request to extend the Right-of-Way Authorization, Section 106, NEPA, and ESA-FWS completion dates on November 13, 2025. The Executive Director determination is posted here.
-
Monthly Status Report for June 2026:The Bureau of Land Management (BLM) missed the May 2, 2026 milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS) and Resource Management Plan (RMP) Amendment. Scoping begins when the NOI is published.
-
Non-conformance Explanation:The Bureau of Land Management (BLM) missed the May 2, 2026 milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS) and Resource Management Plan (RMP) Amendment. Scoping begins when the Notice of Intent is published.