Permitting Action Modification History

Planned
As part of BLM’s effort to align with the Department of the Interior’s July 15, 2025 memorandum, updates to the Mosey Solar Project schedule, including updating the milestone dates on the FAST-41 Dashboard, are necessary to comply with the new requirement that all wind and solar energy project decisions, actions, consultations, and other undertakings be routed through the Office of the Secretary for final review prior to the agency taking action.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 11-21-2025 05-02-2026 --- No
Scoping (Agency Action) 11-21-2025 05-02-2026 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-07-2026 01-15-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-07-2027 12-17-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 08-06-2027 06-19-2028 --- No
Planned
Q4 Update: The BLM internal review and briefing process occurred during the transition period for new BLM and Department Leadership. As such, the review of the project is requiring enhanced coordination. This has affected the NOI and scoping milestones for this project. New NOI milestone date of 12/19/25 and the scoping to 1/19/2026. Due to a Plan Maintenance for Nevada and Northeastern California Sub-Region Greater Sage-Grouse Record of Decision and Approved Resource Management Plan Amendment (2015), a Resource Plan Amendment is no longer required. The Planned Maintenance Action used the best available science and site-specific data, updating the Greater Sage-Grouse Habitat Management Area Map. Habitat Management Area designations were changed to Non-Habitat.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 11-21-2025 12-19-2025 --- No
Scoping (Agency Action) 11-21-2025 01-19-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-07-2027 05-07-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 08-06-2027 08-06-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 11-21-2025 11-21-2025 --- No
Scoping (Agency Action) 11-21-2025 11-21-2025 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-07-2026 08-07-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-07-2027 05-07-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 08-06-2027 08-06-2027 --- No