Agency Milestone Date of 06/13/2025 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
Description:
Environmental Impact Statement with a Resource Management Plan Amendment
Scoping (Agency Action): May to June 2025
Milestones:
-
Non-conformance Explanation:The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
-
Non-conformance Explanation:The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/02/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Description:
Pantheon Solar, LLC proposes to construct, operate, maintain, and eventually decommission a 400-megawatt (MW) solar photovoltaic facility on public lands administered by the U.S. Bureau of Land Management (BLM). The Project’s primary goal is to produce 400-MW of energy annually, which equates to the annual daytime energy needs of approximately 230,000 households. The Project site would encompass approximately 2,682 acres of BLM-administered land located approximately 16 miles west of Ely, Nevada. The Project will include a 500-kilovolt generation tie-line, approximately 6.2 miles in length. Interconnection with the power grid would occur at the Robinson Summit Substation, four miles to the north of the Project site.
The Executive Director granted a Bureau of Land Management request to extend the Right-of-Way Authorization and NEPA completion dates on April 14, 2025. The Executive Director determination is posted here.
-
Non-conformance Explanation:The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.