Permitting Action Modification History

Paused
To ensure the effective administration of public lands, the Bureau of Land Management (BLM) proposes extending the publication of the Notice of Intent in the Federal Register to September 24, 2027. This extension is necessary to provide the project sponsor, Arevia Power, with additional time to engage meaningfully with grazing permittees and address grazing impacts identified during the variance process. This change will create a cascading effect for the other actions.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-02-2025 06-13-2025 11-28-2025 No
Scoping (Agency Action) 07-29-2025 07-29-2025 12-29-2025 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-17-2026 04-24-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 10-28-2026 12-03-2026 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 01-08-2027 02-12-2027 --- No
Planned
The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination, per Secretarial Order 3437, that has affected the timeline for this project. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-02-2025 06-13-2025 11-28-2025 No
Scoping (Agency Action) 07-29-2025 07-29-2025 12-29-2025 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-17-2026 04-24-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 10-28-2026 12-03-2026 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 01-08-2027 02-12-2027 --- No
Planned
The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-02-2025 06-13-2025 07-25-2025 No
Scoping (Agency Action) 07-29-2025 07-29-2025 08-25-2025 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-17-2026 04-24-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 10-28-2026 12-03-2026 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 01-08-2027 02-12-2027 --- No
Planned
The explanation for the milestone date changes is outlined in the Executive Director Determination posted on the project page.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-02-2025 06-13-2025 --- No
Scoping (Agency Action) 07-29-2025 07-29-2025 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-17-2026 04-24-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 10-28-2026 12-03-2026 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 01-08-2027 02-12-2027 --- No
Planned
BLM requires extra time to gather information and prepare the NOI package. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-02-2025 05-16-2025 --- No
Scoping (Agency Action) 07-29-2025 07-29-2025 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-17-2026 03-17-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 10-28-2026 10-28-2026 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 01-08-2027 01-08-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-02-2025 05-02-2025 --- No
Scoping (Agency Action) 07-29-2025 07-29-2025 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-17-2026 03-17-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 10-28-2026 10-28-2026 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 01-08-2027 01-08-2027 --- No