Milestone Extension: Section 106 Review
Cobra MDP Project Section 106 Consultation Concluded Milestone – Alternate Completion Date Rationale
Cobra MDP Project Section 106 Consultation Concluded Milestone – Alternate Completion Date Rationale
Cobra MDP Project Section 106 Consultation Concluded Milestone - Alternate Completion Date Justification
The explanation for the milestone date change was outlined in the Executive Director Determination request submitted to the Permitting Council on March 30, 2026.
This is the original creation of the Section 106 action in the permitting timetable.
The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones.
The MMPA milestones "Publish Proposed ITA in the Federal Register” and “Publish Final ITA Regulations in Federal Register” are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these MMPA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones.
The EFH milestones "NOAA Determines EFH Assessment is Complete" and “NOAA Issues any EFH Conservation Recommendations" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these EFH action milestones. Therefore, an extension of the EFH milestones is requested based upon the extension of BOEM’s EIS milestones.
The ESA milestones "NOAA Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones.
The OCS Air Permit milestones are dependent on BOEM's EIS action milestones. With the shift in the Record of Decision (ROD) date, EPA will accordingly extend the milestone date for issuance of final decision/permit approval of the OCS Air permit.
The Section 408 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to the Section 408 action milestones. Therefore, an extension of the Section 408 milestones is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below.