Milestone Extension: Section 106 Review

Submitted by craig.litteken… on

This is the original creation of the Section 106 action in the permitting timetable.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
Cancelled
POC Name:
Michelle Meyers
POC Title:
Environmental Protection Specialist

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Current Target Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Bay State Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

The Starboard Wind Project will be developed by Bay State Wind LLC, a wholly owned subsidiary of Ørsted. The area to be developed is within the Outer Continental Shelf covered by the Bureau of Ocean Energy Management (BOEM) Renewable Lease No. OCS-A 0500 (Lease Area). The Lease Area is located approximately 14 miles (mi, 22.5 kilometers [km]) south of Martha’s Vineyard, Massachusetts. The Starboard Wind Project represents an update to the Bay State Wind COP, which was submitted in 2019.

The Environmental Review and Permitting Status of this project will be changed to “In Progress” once the Permitting Timetable has been published.

System Comments
Furthest out
Original Target Date: 06/01/2027
Milestone: Consultation initiated with SHPO/THPO (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded (Agency Action) extended by 703
From: 05/04/2029
To: 05/04/2029
Approver Comments
Project sponsor withdrew the project from FAST-41 coverage on 2/20/26.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Consultation initiated with SHPO/THPO (Agency Action)
Current Target Date: