The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below.
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/29/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Description:
Vineyard Mid-Atlantic LLC (the “Project Sponsor”) proposes to develop, construct, and operate an offshore renewable wind energy facility in the Bureau of Ocean Energy Management’s Lease Area Outer Continental Shelf (OCS)-A 0544. OCS-A 0544 is located approximately 38 kilometers (24 miles) offshore from Fire Island, New York. The Project would include a total of 118 wind turbine generators and offshore export cables routed to landfall sites in Long Island, New York to connect to onshore transmission systems in Nassau County, Suffolk County, and/or Queens County, New York.
Original Target Date: 11/24/2026
Milestone: ESA Consultation Concludes (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
ESA Consultation Concludes (Agency Action) extended by 181
From: 11/24/2026
To: 05/24/2027