Milestone Extension: Right-of-Way Authorization (DOI-BLM)
The schedule modification is needed to reconcile errors on the initial CPP schedule as well as delays in receiving a delivery of a final Plan of Development (POD) to the BLM on 4 April 2025. According to BLM Nevada policy under NV IM 2024-019, BLM specialists must be allowed 90 days to review the final POD. NV IM 2024-019 is a Nevada-specific policy for all program areas for projects requiring completion of a National Environmental Policy Act (NEPA) process.