Reject for Administrative Reasons

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

The schedule modification is needed to reconcile errors on the initial CPP schedule as well as delays in receiving a delivery of a final Plan of Development (POD) to the BLM on 4 April 2025. According to BLM Nevada policy under NV IM 2024-019, BLM specialists must be allowed 90 days to review the final POD. NV IM 2024-019 is a Nevada-specific policy for all program areas for projects requiring completion of a National Environmental Policy Act (NEPA) process.

Milestone Extension: Environmental Impact Statement (EIS)

The schedule modification is needed to reconcile errors on the initial CPP schedule as well as delays in receiving a delivery of a final Plan of Development (POD) to the BLM on 4 April 2025. According to BLM Nevada policy under NV IM 2024-019, BLM specialists must be allowed 90 days to review the final POD. NV IM 2024-019 is a Nevada-specific policy for all program areas for projects requiring completion of a National Environmental Policy Act (NEPA) process.

Milestone Extension: Fish and Wildlife Coordination Act Review (DOI – FWS)

The USACE (lead federal agency), in coordination with CPRA (Applicant/Requester), is requesting time extensions for all the planned and in-progress target milestone dates on the permitting dashboard for CPRA’s Mid-Breton Sediment Diversion project.  Additional time is required to perform an adequate assessment of conformance with relevant laws and regulations and to conduct the environmental review (relevant factor).

Milestone Extension: Special Use Permit (FS)

USFS asked to change final issuance date of their special use permit to 11/19/24 to allow for 142 days after the issuance of the Bio Op to incorporate the statutory 142 day objection period for the Forest service permit. 

Milestone Extension: Construction and Operations Plan

The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),

Milestone Extension: Construction and Operations Plan

The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),