Reject for Administrative Reasons

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones.

Milestone Extension: Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consulta

The EFH milestones "NOAA Determines EFH Assessment is Complete" and “NOAA Issues any EFH Conservation Recommendations" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these EFH action milestones.  Therefore, an extension of the EFH milestones is requested based upon the extension of BOEM’s EIS milestones.

Milestone Extension: Endangered Species Act Consultation (NOAA-NMFS)

The ESA milestones "NOAA Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones.

Milestone Extension: Outer Continental Shelf (OCS) Air Permit

The OCS Air Permit milestones are dependent on BOEM's EIS action milestones. With the shift in the Record of Decision (ROD) date, EPA will accordingly extend the milestone date for issuance of final decision/permit approval of the OCS Air permit.

Milestone Extension: Section 408 Permit

The Section 408 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to the Section 408 action milestones. Therefore, an extension of the Section 408 milestones is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below.

Milestone Extension: Section 106 Review

The “Section 106 consultation concluded” milestone is dependent on the timing of consultation meetings with consulting parties – critical milestones in the projects permitting table.

Milestone Extension: Environmental Impact Statement (EIS)

The Department’s issuance of new policies for offshore wind project reviews requires BOEM to integrate revised procedures into the NEPA process for the Vineyard Mid-Atlantic EIS. These new policies include, but are not limited to: