Milestone Extension: Endangered Species Act Consultation (DOI-FWS)
The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones.