EO 13807 Elevation Procedures for Date Extensions: Environmental Impact Statement (EIS)

Submitted by naomi.j.handel… on
Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Status:
In Progress
POC Name:
Randy Steffey
POC Title:
Project Manager

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Milestone Details

A public scoping meeting was held on 7/17/2019 in Williamsburg, Virginia.  The Corps will use the comments received to assist in identifying the significant issues, which should be addressed in the DEIS.  Attendance at the public meeting was not necessary to provide comments.

Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Completed Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Dominion Power Surry-Skiffes Creek-Whealton Corps Permit Application Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/03/2026

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category MIP Only
Major Infrastructure Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, National Park Service

Description:

Virginia Electric and Power Company (Dominion) has proposed an electrical transmission powerline and associated infrastructure, known as Surry-Skiffes Creek-Whealton project. The proposed project involves a 7.76-mile 500 kV overhead transmission powerline from Surry nuclear power plant in Surry County to the proposed Skiffes Creek 500 kV-230 kV-115 kV switching station, on 51 acres of private and commercial property in James City County, and 20.2 miles of 230 kV overhead powerline along an existing right of way from the switching station to Whealton substation in Hampton. In July 2017, the U.S. Army Corps of Engineers (Corps) issued an Individual Permit for the Project under Section 404 of the Clean Water Act (33 U.S.C. 1344) and Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403), as well as a permission letter under RHA Section 408. As part of its review process, the Corps prepared an environmental assessment (EA), which is available at the Corps' project website (https://www.nao.usace.army.mil/ Missions/ Regulatory/ SkiffesCreekPowerLine.aspx). Among other conditions, the permit was issued subject to compliance with a 2017 Memorandum of Agreement (MOA) executed by the Corps; Dominion; and the Acting Assistant Secretary of the Interior for Fish, Wildlife, and Parks (on behalf of the National Park Service (NPS)), among other parties. The MOA, developed through the National Historic Preservation Act Section 106 consultation process, contained stipulations to avoid, minimize, and mitigate impacts to the historic properties in proximity to the proposed project. Dominion proceeded with construction of the project pursuant to the Corps permit and its conditions, including the conditions set forth in the MOA. The Corps permit was challenged in the U.S. District Court for the District of Columbia, which awarded summary judgment to the Corps and upheld the permit decision. That decision was appealed. In National Parks Conservation Association v. Semonite, No. 18-5179, the United States Court of Appeals for the District of Columbia Circuit remanded this action to the district court with instructions to direct the Corps to prepare an EIS pursuant to the National Environmental Policy Act (NEPA). Consistent with the court's decision, Dominion seeks authorization from the Corps for the original proposed project whose construction is approximately 99 percent complete and scheduled for completion by October 2019. On February 26, 2019, Dominion Energy electrically energized the Project.

field_status
System Comments
The following milestones have been extended 30 days past the current final target completion date for the following Action: Environmental Impact Statement (EIS)

-Issuance of Lead Agency Record of Decision

The responsible agency of this Action, Department of the Army US Army Corps of Engineers - Regulatory, must indicate if Elevation Procedures were used for this extension.
Missed Date Process
No
Missed Date Triggered by Extension
No
Response Date
Original Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: