Agency Milestone Date of 02/17/2023 for Final Verification/Permit Decision Rendered (Agency Action) has passed by 1 business days
Description:
Section 10 Rivers and Harbors Act/Section 404 Clean Water Act: The Secretary of the Army, acting through the U.S. Army Corps of Engineers (Corps), has authority to permit the discharge of dredged or fill material in waters of the U.S. under Section 404 of the Clean Water Act (CWA). The Corps also has authority to permit work and the placement of structures in navigable waters of the U.S. under Sections 9 and 10 of the Rivers and Harbors Act of 1899 (RHA) (see 33 CFR 320.2).
Milestones:
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 12/12/2022
-
Monthly Status Report for May 2023:USACE continues to review the information provided in the Biological Opinion (BO) and comments received from the public notice. USACE final decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification. USACE is awaiting the 401 water quality certification , before making a final permit decision under Section 404 of the Clean water Act and Section 10 of the Rivers and Harbors Act of 1899, and anticipate making these decisions by the current milestone reflected on the dashboard of June 30, 2023.
-
Monthly Status Report for April 2023:USACE continues to review the information provided in the revised BO and comments received from the most recent public notice. USACE final permit decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification. USACE is awaiting the 401 water quality certification, before rendering a final permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA).
-
Monthly Status Report for March 2023:The USACE permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO. The FWS revised BO was issued on February 28, 2023. USACE has identified an alternative completion date of April 29, 2023, for their final Section 10/404 permit decision.
-
Non-conformance Explanation:The U.S. Army Corps of Engineer’s (USACE’s) permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (the “Section 10/404 final completion date) is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO. Furthermore, on December 5, 2022, the project sponsor provided revised information related regulated discharges, because of which USACE on December 12, 2022, issued a supplemental public notice soliciting comments on the revised information. Based on both the extension of ESA consultation and the need for additional time to review the project sponsor’s revised information submittal, pursuant to 42 USC § 4370m-2(c)(2)(d)(i)(IV), USACE timely requested Executive Director authorization to modify the Section 10/404 final completion date from February 17, 2023 to April 18, 2023. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of January 18, 2023 (30 days prior to the posted completion date). Therefore, USACE could not modify the permitting timetable to reflect the extended completion date. Because USACE was unable to meet the posted completion date, pursuant to 42 USC § 4370m-2(c)(2)(F), USACE appropriately established an alternative completion date for the Section 10/404 action and will adhere to the statutory procedures required by section 4370m-2(c)(2)(F) until the agency takes final action on the Section 10/404 permit.
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 12/12/2022
-
Monthly Status Report for May 2023:USACE continues to review the information provided in the Biological Opinion (BO) and comments received from the public notice. USACE final decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification. USACE is awaiting the 401 water quality certification , before making a final permit decision under Section 404 of the Clean water Act and Section 10 of the Rivers and Harbors Act of 1899, and anticipate making these decisions by the current milestone reflected on the dashboard of June 30, 2023.
-
Monthly Status Report for April 2023:USACE continues to review the information provided in the revised BO and comments received from the most recent public notice. USACE final permit decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification. USACE is awaiting the 401 water quality certification, before rendering a final permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA).
-
Monthly Status Report for March 2023:The USACE permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO. The FWS revised BO was issued on February 28, 2023. USACE has identified an alternative completion date of April 29, 2023, for their final Section 10/404 permit decision.
-
Non-conformance Explanation:The U.S. Army Corps of Engineer’s (USACE’s) permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (the “Section 10/404 final completion date) is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO. Furthermore, on December 5, 2022, the project sponsor provided revised information related regulated discharges, because of which USACE on December 12, 2022, issued a supplemental public notice soliciting comments on the revised information. Based on both the extension of ESA consultation and the need for additional time to review the project sponsor’s revised information submittal, pursuant to 42 USC § 4370m-2(c)(2)(d)(i)(IV), USACE timely requested Executive Director authorization to modify the Section 10/404 final completion date from February 17, 2023 to April 18, 2023. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of January 18, 2023 (30 days prior to the posted completion date). Therefore, USACE could not modify the permitting timetable to reflect the extended completion date. Because USACE was unable to meet the posted completion date, pursuant to 42 USC § 4370m-2(c)(2)(F), USACE appropriately established an alternative completion date for the Section 10/404 action and will adhere to the statutory procedures required by section 4370m-2(c)(2)(F) until the agency takes final action on the Section 10/404 permit.
PROJECT WEBSITE: https://www.mountainvalleypipeline.info/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/23/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, National Park Service
Department of the Interior, Bureau of Land Management
Department of Agriculture, US Forest Service
Description:
On August 18, 2022, Mountain Valley Pipeline, LLC submitted a FAST-41 Initiation Notice for the outstanding federal environmental reviews and authorizations for the project following associated court decisions. A determination of FAST-41 coverage was made on September 1, 2022.
The project was previously in the initial inventory of FAST-41 covered projects designated by the Executive Director of the Federal Permitting Improvement Steering Council in September 2016 before being closed out on the Permitting Dashboard in late 2017.
As described in the project sponsor’s FAST-41 Initiation Notice, the project includes the construction of approximately 304 miles of natural gas pipeline in West Virginia and Virginia, three new compressor stations in West Virginia, metering stations, taps, and appurtenant facilities. The project would provide up to 2,000,000 dekatherms per day of firm natural gas transportation service from northern West Virginia to southwestern Virginia.