USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Supplemental Environmental Impact Statement (EIS): Supplemental EIS process concluded (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 03/30/2023 for Supplemental EIS process concluded (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Department of Energy
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Brian Lavoie
POC Title:
Sr. Natural Gas Analyst

Description:

On April 15, 2021, DOE’s Office of Fossil Energy and Carbon Management issued a Rehearing Order in its docket for the Alaska LNG Project LLC (Docket No. 14-96-LNG). In the Rehearing Order, DOE granted a request for rehearing of a final order issued to Alaska LNG Project LLC (Alaska LNG) for the purpose of conducting two Alaska-specific environmental studies (collectively, the Alaska environmental study proceeding).

On July 2, 2021, DOE issued a Notice of Intent (NOI) to prepare a supplemental environmental impact statement (SEIS) for the Alaska environmental study proceeding (DOE/EIS–0512–S1), consistent with the National Environmental Policy Act (NEPA) (see 86 Fed. Reg. 35,280). As set forth in the NOI, the SEIS will include analysis of potential environmental impacts associated with natural gas production on the North Slope of Alaska and a life cycle analysis (LCA) calculating the greenhouse gas (GHG) emissions for LNG exported from the proposed Alaska LNG Project. On August 24, 2021, DOE issued a Notice of Schedule for Supplemental Environmental Impact Statement.

Additionally, DOE’s Alaska LNG order has been challenged in the U.S. Court of Appeals for the District of Columbia Circuit (Sierra Club v. U.S. Dep’t of Energy, Case No. 20-1503).  That case is currently being held in abeyance, pending further order of the court.  All court filings are available on the D.C. Circuit’s docket through Pacer (Case  No. 20-1503). (A Pacer account is required – the login page is at PACER: Login (uscourts.gov))

DOE determined that it was necessary for the National Energy Technology Laboratory (NETL), which is conducting the SEIS, to conduct additional modeling on an issue central to both studies in the SEIS—the options associated with managing carbon dioxide (CO2) produced with, and removed from, the natural gas supplying the proposed Alaska LNG Project on the North Slope of Alaska. NETL’s analysis will determine the range of potential environmental and production impacts associated with the different carbon management options. NETL will use this analysis in assessing the technical viability of producing natural gas to support the Project, as well as any secondary effects to North Slope oil production. DOE has determined that this additional technical analysis will extend the original SEIS schedule by approximately 60 days. On February 25, 2022, DOE posted a Notice of Amended Schedule in its docket for Alaska LNG Project LLC, Docket No. 14-96-LNG. On October 28, 2022, DOE posted a Second Notice of Amended Schedule in this docket.

When additional information about the SEIS is available, updates will be posted on both the FAST-41 Dashboard and in DOE’s above-referenced docket for Alaska LNG.

Milestones:

Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action)
Completed Date:
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action)
Completed Date:
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action)
Completed Date:
Supplemental EIS process concluded (Agency Action)
  • Monthly Status Report for April 2023:
    Notified by DOE that this action was completed on 4/13/23.
  • Non-conformance Explanation:
    As stated in DOE's Third Notice of Amended Schedule for Supplemental Environmental Impact Statement, dated March 29, 2023, due to the range of issues addressed in the Final SEIS, DOE has determined that it will need no more than 21 days to complete the Final Order and NEPA Record of Decision and amends the schedule for completion with a final date of April 20, 2023.
Current Target Date:
Milestone
Supplemental EIS process concluded (Agency Action)
  • Monthly Status Report for April 2023:
    Notified by DOE that this action was completed on 4/13/23.
  • Non-conformance Explanation:
    As stated in DOE's Third Notice of Amended Schedule for Supplemental Environmental Impact Statement, dated March 29, 2023, due to the range of issues addressed in the Final SEIS, DOE has determined that it will need no more than 21 days to complete the Final Order and NEPA Record of Decision and amends the schedule for completion with a final date of April 20, 2023.
Current Target Date:
Project

PROJECT WEBSITE: http://alaska-lng.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/13/2023

14 out of 14

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Energy

LEAD AGENCY
Department of Energy

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Federal Energy Regulatory Commission

Federal Energy Regulatory Commission

Department of Homeland Security

Department of Homeland Security, US Coast Guard

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Interior

Department of the Interior, National Park Service

Description:

The Alaska LNG Project is comprised of the following integrated and interdependent facilities:  a liquefied natural gas (LNG) terminal in Southcentral Alaska designed to produce up to 20 million metric tons per annum of LNG; an approximately 807-mile, 42-inch diameter gas pipeline; a gas treatment plant (GTP) within the Prudhoe Bay Unit (PBU) on the North Slope; an approximately 1-mile, 60-inch diameter gas transmission line connecting the GTP to the PBU gas production facility; and an approximately 63 mile, 32-inch diameter gas transmission line connecting the GTP to the Point Thomson gas production facility.  The mainline of the Alaska LNG Project will traverse over 800 miles from the GTP on the North Slope of Alaska through several boroughs before it crosses Cook Inlet and connects with the liquefaction plant and marine terminal in Nikiski, Alaska. 

Fast-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

DOE litigation re Natural Gas Export Authorization

Alaska LNG Project LLC - FE Dkt. No. - 14-96-LNG | Department of Energy

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Alaska LNG Project.  

Additional Federal Agency Permitting Timetable for the Alaska LNG Project 
Responsible Agency Federal Permit/Review Status Applicable Timelines
US Coast Guard Letter of Recommendation Complete Receipt of Letter of Intent:  May 15, 2014
Receipt of Waterway Suitability Assessment:  March 18, 2016
Letter of Recommendation to FERC:  August 17, 2016

Update: 

Federal environmental review and authorization for the Alaska LNG Project was completed on September 16, 2020. However, on April 15, 2021, the Department of Energy (DOE), a cooperating agency on this project, granted a request for rehearing of a final order issued to Alaska LNG Project LLC for the export of liquefied natural gas produced from Alaskan sources to non-free trade agreement countries, pursuant to the Natural Gas Act (NGA). In the Rehearing Order, DOE stated that it was granting rehearing for the purpose of conducting two Alaska-specific environmental studies (collectively, the Alaska environmental study proceeding). To this end, DOE prepared a supplemental Environmental Impact Statement (SEIS) for the Alaska environmental study proceeding (DOE/EIS-0512-S1), consistent with the National Environmental Policy Act. Based on its findings from the SEIS—including the associated public process—DOE intends to issue an order under section 3(a) of the NGA, in which DOE presents its findings and conclusions, by March 30, 2023. DOE may decide to modify, set aside, or confirm the Alaska LNG Order (Order No. 3643-A), in whole or in part. Because DOE’s supplemental environmental review and subsequent order are currently the only pending Federal actions on this project and all other federal reviews and authorizations—including the Federal Energy Regulatory Commission’s (FERC) Authorization for Liquefied Natural Gas Terminal Facilities, Onshore or in State Waters”—are complete, DOE is replacing FERC as the NEPA lead agency for this SEIS.

The Executive Director granted a DOE request to extend the completion dates for DOE actions associated with the supplemental environmental impact statement. The Executive Director determination is available here.

The Executive Director granted a DOE request to extend the completion date associated with the supplemental environmental impact statement on January 13, 2023. The Executive Director determination is available here.

field_status
System Comments
Agency Milestone Date of 03/30/2023 for Supplemental EIS process concluded (Agency Action) has passed by 1 business days
Approver Comments
DOE published a new date to the court docket that extends the final SEIS milestone to 4/20/23. The milestone was due on 3/30/23 and notice was given on 3/29/23. DOE is aware that the action will be in nonconformance.
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
Agency Notified Date
New Milestone
Supplemental EIS process concluded (Agency Action)
  • Monthly Status Report for April 2023:
    Notified by DOE that this action was completed on 4/13/23.
  • Non-conformance Explanation:
    As stated in DOE's Third Notice of Amended Schedule for Supplemental Environmental Impact Statement, dated March 29, 2023, due to the range of issues addressed in the Final SEIS, DOE has determined that it will need no more than 21 days to complete the Final Order and NEPA Record of Decision and amends the schedule for completion with a final date of April 20, 2023.
Current Target Date:
Response Date
Reporting Agency