Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Submitted by carlos_arandia on

Sponsor is not concerned with the date change, no other aspects of permitting timetable are affected. Justification for delay documented under the action in the dashboard. The DOI Cerpo is aware of the delay.    
 

Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: http://www.ryedevelopment.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/17/2019

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, Bureau of Reclamation

Description:

Swan Lake North Pumped Storage (Project No. 13318) is a proposal to construct an original, closed-loop pumped storage project that would provide 393 MW of generation capacity in Oregon.  The proposed project would consist of, among other facilities, an upper and lower reservoir with active storage capacities of 2,562 and 2,581 acre-feet, respectively, a high-pressure penstock, three low-pressure penstocks, a powerhouse, a substation, and a 32.8-mile-long, 230-kilovolt transmission line. 

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

Last updated November 22, 2019

field_status
System Comments
Furthest out Original Target Date: 07/29/2019
Milestone: Issuance of decision for permit/approval

Requested extensions greater than 30 days for this Action are shown below:

Issuance of decision for permit/approval by 80 days
From: 09/12/2019
To: 10/17/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: