USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date: Endangered Species Act Consultation (DOI-FWS)

Submitted by Anonymous on

Final Required Milestone Date of 05/10/2021 for Conclusion of ESA Consultation has passed by 5 business days

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under NEPA
Status:
Paused
POC Name:
Paul Henson
POC Title:
State Supervisor
POC Email:

Description:

The Project entails development of a liquid natural gas shipping terminal in Coos Bay, Oregon, and a 230-mile pipeline across private and Federal lands in southwestern Oregon. The Service completed ESA consultation in January 2020 and determined the Project would adversely affect western snowy plover, Pacific fisher, California marten, several listed plant species, northern spotted owl, and marbled murrelet. Although impacts to the latter two species would be substantial, the Service concluded the Project was not likely to jeopardize any species. FERC then selected a Project alignment that was not analyzed in the agency’s prior Biological Assessment. Consequently, on June 23, 2020, FERC requested reinitiation of consultation. After thoroughly reviewing the information FERC provided, the Service notified FERC on July 7, 2020, that reinitiation of consultation cannot begin until additional information and a BA is received. Both agencies agreed to a collaborative process to develop the new information as quickly as possible, contingent on cooperation from Pembina. On December 4, the Service received from FERC the information needed to reinitiate consultation on this project and is reviewing that information to ensure it is complete.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Completed Date:
ESA Consultation Concludes (Agency Action)
  • Monthly Status Report for April 2021:
    FWS developed the current consultation process in coordination with FERC, BLM and Pembina, to include time for BLM to review draft T&Cs and propose specific revisions that would address its concerns.  The extension will allow time to review the draft BO by FERC, BLM, and Pembina before it is finalized. The new target will not affect overall project schedule. In addition, we understand that the applicant may pause work on the project so we will continue to closely coordinate with all parties.
Current Target Date:
Milestone
ESA Consultation Concludes (Agency Action)
  • Monthly Status Report for April 2021:
    FWS developed the current consultation process in coordination with FERC, BLM and Pembina, to include time for BLM to review draft T&Cs and propose specific revisions that would address its concerns.  The extension will allow time to review the draft BO by FERC, BLM, and Pembina before it is finalized. The new target will not affect overall project schedule. In addition, we understand that the applicant may pause work on the project so we will continue to closely coordinate with all parties.
Current Target Date:
Project

PROJECT WEBSITE: Jordan Cove LNG

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2020

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Jordan Cove LNG Project (Docket No. CP17-495-000) includes the construction and operation of a liquefied natural gas (LNG) export terminal on the North Spit of Coos Bay in Coos County, Oregon.  The terminal would include gas inlet facilities, a metering station, a gas conditioning plant, five liquefaction trains and associated equipment, two full-containment LNG storage tanks, an LNG transfer line, LNG ship loading facilities, a marine slip, a marine offloading facility, a new access channel between the Coos Bay Navigation Channel and the new marine slip, and enhancements to the existing Coos Bay Navigation Channel at four turns.  In addition, the terminal would include emergency and hazard, electrical, security, control, and support systems, administrative buildings, and a temporary workforce housing facility.  The LNG terminal would be designed to liquefy about 1.04 billion cubic feet per day of LNG for export to markets across the Pacific Rim.

The Pacific Connector Gas Pipeline (Docket No. CP-17-494) includes the construction and operation an approximately 229-mile-long, 36-inch-diameter interstate natural gas transmission pipeline and associated aboveground facilities.  The pipeline would originate near Malin in Klamath County, Oregon, traverse Douglas and Jackson Counties, and terminate (at the LNG Terminal) in Coos County, Oregon.  The pipeline would be capable of transporting about 1.2 billion cubic feet per day of natural gas.  The associated aboveground facilities would include the new Klamath Compressor Station (61,500 horsepower) near Malin, Oregon; 3 new meter stations; 5 new pig launchers and receivers; 17 mainline block valves; and a gas control communication system.

Fast-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Jordan Cove LNG Project.  

Additional Federal Agency Authorization Timetable for the Jordan Cove LNG and Pacific Connector Gas Pipeline Project
Agency Permit Status Applicable Timelines
U.S. Coast Guard Letter of Recommendation Completed Receipt of Letter of Intent:  April 2006
Receipt of Water Suitability Assessment:  10/1/17
Letter of Recommendation to FERC:  5/10/18  

 

Last updated March 27, 2021

field_status
System Comments
Final Required Milestone Date of 05/10/2021 for Conclusion of ESA Consultation has passed by 5 business days
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
ESA Consultation Concludes (Agency Action)
  • Monthly Status Report for April 2021:
    FWS developed the current consultation process in coordination with FERC, BLM and Pembina, to include time for BLM to review draft T&Cs and propose specific revisions that would address its concerns.  The extension will allow time to review the draft BO by FERC, BLM, and Pembina before it is finalized. The new target will not affect overall project schedule. In addition, we understand that the applicant may pause work on the project so we will continue to closely coordinate with all parties.
Current Target Date: