USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date: Section 408 Permit

Submitted by Anonymous on

Final Required Milestone Date of 03/09/2021 for Issuance of decision for permit/approval has passed by 5 business days

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Paused
POC Name:
Sally Bird-Gauven
POC Title:
Section 408 Program Manager

Description:

The Portland District is reviewing a Department of Army individual permission pursuant to 33 USC Section 408 for potential adverse impacts to the Coos Bay Federally Authorized Navigation Channel. Those features, include: the pile dike field, pipeline construction under the navigation channel, slip and access channel, marine offloading facility, dredging in the Coos Bay Federal Navigation Channel, dredged material disposal management and temporary dredge material disposal pipe placement in the Federal Navigation Channel. This work is associated with Jordan Cove LNG Terminal and Pacific Connector Gas Pipeline.  

On 18 Nov 2020, USACE moved this action to “paused” status until such time our agency receives either a decision on or a date for a decision on the Section 401 Water Quality Certification/waiver

 

 

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Completeness Determination (Agency Action)
Current Target Date:
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

The final milestone target date is dependent on the receipt of compliance documentation regarding Tribal Trust Responsibilities, Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and Essential Fish Habitat compliance pursuant to the Magnuson-Stevens Fishery Conservation and Management Act from the FERC; the receipt of a Coastal Zone Management Act concurrence determination or presumed concurrence determination from the Oregon Department of Land Conservation and Development;  the receipt of a Section 401 Water Quality Certification/waiver from the Oregon Department of Environmental Quality or a waiver of the certification; and the receipt of a complete application from the applicant.  If the information above is not received from the FERC, state or Federal agencies, and/or the applicant at least 60 days prior to the milestone target date, the Corps will consider the delay and adjust the decision deadline to allow a 60-day review once all required documentation/information is received.  In the meantime, the Corps will continue its evaluation concurrent with the federal environmental review process as much as practicable.

 

Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

The final milestone target date is dependent on the receipt of compliance documentation regarding Tribal Trust Responsibilities, Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and Essential Fish Habitat compliance pursuant to the Magnuson-Stevens Fishery Conservation and Management Act from the FERC; the receipt of a Coastal Zone Management Act concurrence determination or presumed concurrence determination from the Oregon Department of Land Conservation and Development;  the receipt of a Section 401 Water Quality Certification/waiver from the Oregon Department of Environmental Quality or a waiver of the certification; and the receipt of a complete application from the applicant.  If the information above is not received from the FERC, state or Federal agencies, and/or the applicant at least 60 days prior to the milestone target date, the Corps will consider the delay and adjust the decision deadline to allow a 60-day review once all required documentation/information is received.  In the meantime, the Corps will continue its evaluation concurrent with the federal environmental review process as much as practicable.

 

Project

PROJECT WEBSITE: Jordan Cove LNG

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2020

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Jordan Cove LNG Project (Docket No. CP17-495-000) includes the construction and operation of a liquefied natural gas (LNG) export terminal on the North Spit of Coos Bay in Coos County, Oregon.  The terminal would include gas inlet facilities, a metering station, a gas conditioning plant, five liquefaction trains and associated equipment, two full-containment LNG storage tanks, an LNG transfer line, LNG ship loading facilities, a marine slip, a marine offloading facility, a new access channel between the Coos Bay Navigation Channel and the new marine slip, and enhancements to the existing Coos Bay Navigation Channel at four turns.  In addition, the terminal would include emergency and hazard, electrical, security, control, and support systems, administrative buildings, and a temporary workforce housing facility.  The LNG terminal would be designed to liquefy about 1.04 billion cubic feet per day of LNG for export to markets across the Pacific Rim.

The Pacific Connector Gas Pipeline (Docket No. CP-17-494) includes the construction and operation an approximately 229-mile-long, 36-inch-diameter interstate natural gas transmission pipeline and associated aboveground facilities.  The pipeline would originate near Malin in Klamath County, Oregon, traverse Douglas and Jackson Counties, and terminate (at the LNG Terminal) in Coos County, Oregon.  The pipeline would be capable of transporting about 1.2 billion cubic feet per day of natural gas.  The associated aboveground facilities would include the new Klamath Compressor Station (61,500 horsepower) near Malin, Oregon; 3 new meter stations; 5 new pig launchers and receivers; 17 mainline block valves; and a gas control communication system.

Fast-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Jordan Cove LNG Project.  

Additional Federal Agency Authorization Timetable for the Jordan Cove LNG and Pacific Connector Gas Pipeline Project
Agency Permit Status Applicable Timelines
U.S. Coast Guard Letter of Recommendation Completed Receipt of Letter of Intent:  April 2006
Receipt of Water Suitability Assessment:  10/1/17
Letter of Recommendation to FERC:  5/10/18  

 

Last updated January 7, 2021

field_status
System Comments
Final Required Milestone Date of 03/09/2021 for Issuance of decision for permit/approval has passed by 5 business days
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Milestone Details

The final milestone target date is dependent on the receipt of compliance documentation regarding Tribal Trust Responsibilities, Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and Essential Fish Habitat compliance pursuant to the Magnuson-Stevens Fishery Conservation and Management Act from the FERC; the receipt of a Coastal Zone Management Act concurrence determination or presumed concurrence determination from the Oregon Department of Land Conservation and Development;  the receipt of a Section 401 Water Quality Certification/waiver from the Oregon Department of Environmental Quality or a waiver of the certification; and the receipt of a complete application from the applicant.  If the information above is not received from the FERC, state or Federal agencies, and/or the applicant at least 60 days prior to the milestone target date, the Corps will consider the delay and adjust the decision deadline to allow a 60-day review once all required documentation/information is received.  In the meantime, the Corps will continue its evaluation concurrent with the federal environmental review process as much as practicable.