Endangered Species Act Consultation (DOI-FWS)

Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Complete
POC Name:
Paul Henson
POC Title:
State Supervisor
POC Email:
Action Outcome:
Biological opinion issued

Description:

We are modifying Milestonte 3 of the ESA consultation to extend the consultation period 30 days. Additional time needed for Consultation due to (1) the amount and scope of additional information about the Project being relayed to the Service by the action agencies, other agencies, tribal entities and the Applicant; (2) the increasing complexity of assessing impacts and their significance based on this additional information; and (3) recent revisions to regulations that implement section 7 of the ESA, that must be applied to consultations underway as of October 28, 2019. The extension should not affect the schedule for the revised date for the EIS.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Informal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Completed Date: