Additional information required of, and provided by, the Project Sponsor results in a delay of slightly more than one month in the development of the DEIS, and cascading delays in the FEIS and ROD. BOEM prepared a draft EIS based on the COP updates available in November 2022 and completed a cooperating agency review of the partial DEIS in June 2023. The Project Sponsor submitted a COP update in Nov 2022 and an additional COP update in July 2023. BOEM cannot complete the DEIS until all the Project Sponsor’s complete revisions to the PDE and associated reports have been provided, reviewed, and incorporated into the analysis in the DEIS. The PDE changes in the COP update include additional dredging, updated cable routes, and refinement of O&M facility details. This additional information is required for the DEIS, which will shift the date for the ROD. Since the Section 10/404 final milestone is dependent upon the ROD, the final Section 10/404 milestone is shifting accordingly.
Cooperating under NEPA
Milestones:
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 06/26/2024 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 06/21/2024 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 04/01/2024 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 02/01/2024 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 03/08/2024
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 06/26/2024 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 06/21/2024 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 04/01/2024 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 02/01/2024 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 03/08/2024
PROJECT WEBSITE: http://www.uswindinc.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/03/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Description:
The Maryland Offshore Wind Project involves construction of a renewable energy generation facility and the associated electricity transmission infrastructure to connect the generation to the regional electric grid.
US Wind is proposing the development and eventual decommissioning of the Maryland Offshore Wind Project (the Project), an offshore wind energy project (including an Operations and Maintenance Facility) of up to approximately 2 gigawatts of nameplate capacity within OCS-A 0490 (the Lease). The Lease area covers 79,707 acres with the western edge located approximately 18.5 km (11.5 miles) off the coast of Maryland on the Outer Continental Shelf.
Under a Project Design Envelope (PDE) approach, the Project could include as many as 121 wind turbine generators (WTG), up to four offshore substations (OSS), and one meteorological tower (Met Tower) in the Lease area, with a total of 126 structure in a gridded array pattern distributed across the Lease area. The gridded array comprises 13 east-west rows with 0.87 mile spacing between structures, and 18 columns oriented approximately north-northeast to south-southwest with 1.17 mile spacing. Inter-array cables would run in a radial fashion from the WTGs toward the OSS locations. The Met Tower is proposed in a location along the southern edge of the Lease area.
Up to 4 offshore export cables are included in the PDE. The export cables consist of an offshore portion, the Offshore Export Cables, from the Lease area to the landing location, through a transition vault to the onshore portion, and the Onshore Export Cables that connect to the Point of Interconnection (POI). The preferred route of the offshore export cable, known as Offshore Export Cable Corridor 1, would exit the Lease area from the northwestern portion of the Lease area, and traverse northeasterly to shore making landfall south of the Indian River Inlet at 3R’s Beach in the Delaware Seashore State Park. From there the onshore export submarine cables would extend through Indian River Bay via Onshore Export Cable Corridor 1 and connect to the POI at the Delmarva Power and Light Indian River Substation near Millsboro, Delaware. Additional options within the PDE include the offshore export cables making landfall at the Tower Road parking lot, north of Indian River inlet, and crossing over land to the Indian River Substation or alternate POIs. The PDE also includes land-based cable corridors, if a terrestrial route is pursued, which would be co-located in existing rights-of-way.
The Operations and Maintenance Facility (O&M Facility) is proposed to be in Ocean City, Maryland, and would include a 15,000 square foot combined office and warehouse building with associated parking, outdoor storage, and crew comfort and support areas to stage operations and maintenance personnel. The O&M Facility would include crew transfer vessel (CTV) quayside and berthing areas, and would also house a Marine Coordination Center, which would serve to monitor the status of the WTGs and OSSs via SCADA systems, plan maintenance operations and dispatch CTVs, monitor marine activity in the Project area, coordinate drills and exercises, and communicate with outside agencies.
Update:
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the COP, Section 106, MMPA, Section 10/404, and Section 408 actions completion date on August 17, 2023. The Executive Director determination is posted here.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 06/26/2024 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 06/21/2024 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 04/01/2024 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 02/01/2024 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 03/08/2024
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Completed Date: 06/26/2024 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 06/21/2024 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 04/01/2024 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 02/01/2024 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 03/08/2024
Original Target Date: 09/24/2024
Milestone: Final Verification/Permit Decision Rendered (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Final Verification/Permit Decision Rendered (Agency Action) extended by 66
From: 10/24/2024
To: 11/29/2024