Maryland Offshore Wind Project
PERMITTING DASHBOARD PROJECT POSTING DATE: MARCH 28, 2022PROJECT WEBSITE: http://www.uswindinc.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/03/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Description:
US Wind is proposing the development and eventual decommissioning of the Maryland Offshore Wind Project, an offshore wind energy project (including an Operations and Maintenance Facility) of up to approximately 2 gigawatts of nameplate capacity within OCS-A 0490 (the Lease). The Lease area covers 79,707 acres with the western edge located approximately 18.5 km (11.5 miles) off the coast of Maryland on the Outer Continental Shelf.
Update:
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the COP, Section 106, MMPA, Section 10/404, and Section 408 actions completion date on August 17, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the COP (BOEM), MMPA (NMFS), Section 10/404 (USACE), Section 408 (USACE) actions completion date on July 01, 2024. The Executive Director determination is posted here.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|