Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation

Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Complete
POC Name:
Keith Hanson
POC Title:
Marine Habitat Resource Specialist
Action Outcome:
One or more EFH conservation recommendations are issued

Milestones:

EFH Consultation Request Submitted – EFH Assessment (Agency Action)
  • Monthly Status Report for March 2024:
    Additional information related to dredging for the cable route was still outstanding at the beginning of the month. Sponsor submittal anticipated by the end of the month. The information is required for the EFH consultation.  
  • Monthly Status Report for February 2024:
    Completion of EFH consultation will be dependent on completing analysis of dredging for the onshore cable route. There is ongoing coordination between agencies and the sponsor to ensure information sufficient to conclude consultation.
  • Monthly Status Report for January 2024:
    Alternative milestone is Feb 2, 2024 for NOAA determines EFH Assessment is Complete (Agency Action). BOEM submitted revised EFH package to NMFS on January 26, 2024.
  • Monthly Status Report for December 2023:
    BOEM submitted a revised EFH consultation request to NMFS on Dec 15, 2023. NMFS is reviewing the revised BA to determine if the package can be 'deemed complete' to meet the subsequent milestone of Jan 3, 2024
  • Monthly Status Report for November 2023:
    Alternative milestone shifting from Dec 4, 2023 to Jan 3, 2024 to allow BOEM time to gather information from developer and update the consultation documents. Issues include: inconsistency with USACE permit application (which was submitted after most of the consultation documents were written); clarifications about ports and O&M facility; need more info from US Wind about disposition of dredged material.
  • Monthly Status Report for October 2023:
    BOEM and NMFS coordinated regarding needed information to update consultation documents. BOEM is coordinating with the sponsor to collect required information.
  • Monthly Status Report for September 2023:
    BOEM and NMFS coordinated regarding needed information to update consultation documents. BOEM is coordinating with the sponsor to collect required information.
  • Monthly Status Report for August 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Monthly Status Report for July 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Monthly Status Report for June 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Non-conformance Explanation:
    The original date entered into the dashboard for this milestone was misaligned with BOEM's nominal schedule. In the nominal schedule, this milestone typically is concurrent with the start of the NMFS's DEIS review. That date is anticipated to be June 2, 2023, not May 19 as previously indicated.
Alternative Completion Date:
NOAA determines EFH Assessment is Complete (Agency Action)
Alternative Completion Date:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
Alternative Completion Date: