Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 08-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 09-14-2023 --- Yes
Publication of Public Notice (Agency Action) 08-04-2023 10-06-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 01-03-2025 --- Yes
In Progress
A commensurate extension of the Section 10/404/408 final completion date is requested based upon the extension of the ROD milestone. Factors that inform the USACE final decision include the conclusion of Delaware Natural Resources and Environmental Control's (DNREC) Section 401 water quality certification (WQC) process.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 08-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 09-14-2023 --- Yes
Publication of Public Notice (Agency Action) 08-04-2023 10-06-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 01-03-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 08-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 09-14-2023 --- Yes
Publication of Public Notice (Agency Action) 08-04-2023 10-06-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 11-29-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 08-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 09-14-2023 --- Yes
Publication of Public Notice (Agency Action) 08-04-2023 10-06-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 11-29-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 08-30-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 09-14-2023 --- No
Publication of Public Notice (Agency Action) 08-04-2023 10-06-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 11-29-2024 --- No
Planned
Additional information required of, and provided by, the Project Sponsor results in a delay of slightly more than one month in the development of the DEIS, and cascading delays in the FEIS and ROD. BOEM prepared a draft EIS based on the COP updates available in November 2022 and completed a cooperating agency review of the partial DEIS in June 2023. The Project Sponsor submitted a COP update in Nov 2022 and an additional COP update in July 2023. BOEM cannot complete the DEIS until all the Project Sponsor’s complete revisions to the PDE and associated reports have been provided, reviewed, and incorporated into the analysis in the DEIS. The PDE changes in the COP update include additional dredging, updated cable routes, and refinement of O&M facility details.  This additional information is required for the DEIS, which will shift the date for the ROD.  Since the Section 10/404 final milestone is dependent upon the ROD, the final Section 10/404 milestone is shifting accordingly.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 08-30-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 09-14-2023 --- No
Publication of Public Notice (Agency Action) 08-04-2023 10-06-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 11-29-2024 --- No
Planned
The applicant has indicated that they will be delayed in submitting their permit application and will not make the original target date. There was a previous delay to 7/26/23 and now there is another one month applicant delay to 8/30/23. Subsequent interim milestones were updated accordingly to reflect the applicant delay. The complete application milestone and the public notice milestone were adjusted accordingly based on the revised application submittal target date. The USACE district project manager has coordinated the revised application submittal date with the applicant. The applicant has agreed to the revised interim milestones. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 08-30-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 09-14-2023 --- No
Publication of Public Notice (Agency Action) 08-04-2023 10-06-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 10-24-2024 --- No
Planned
The schedule has been adjusted in accordance with BOEM's revised schedule.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 07-26-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 08-10-2023 --- No
Publication of Public Notice (Agency Action) 08-04-2023 09-01-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 10-24-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-30-2023 06-30-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-15-2023 07-15-2023 --- No
Publication of Public Notice (Agency Action) 08-04-2023 08-04-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-24-2024 09-24-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) --- 06-30-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) --- 07-15-2023 --- No
Publication of Public Notice (Agency Action) --- 08-04-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) --- 09-24-2024 --- No