Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Submitted by georgeann.smal… on

The schedule modification is needed to reconcile errors on the initial CPP schedule as well as delays in receiving a delivery of a final Plan of Development (POD) to the BLM on 4 April 2025. According to BLM Nevada policy under NV IM 2024-019, BLM specialists must be allowed 90 days to review the final POD. NV IM 2024-019 is a Nevada-specific policy for all program areas for projects requiring completion of a National Environmental Policy Act (NEPA) process. The purpose of the IM is to outline the BLM NV NEPA project management process with greater clarity, incorporate improvements learned over time and include changes to the 2023 Fiscal Responsibility Act (FRA) (Public Law 118-5 Section 107(f) changes to NEPA. The NV IM requires that the Project provided the Supplemental Information Reports and the Supplemental Environmental Reference (SIRs & SERs) to ensure a thorough review and completeness of the POD to mitigate delays in the formal NEPA process.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Ronnie McAboy
POC Title:
District Manager
POC Email:

Milestones:

Initial application received (Agency Action)
Completed Date:
Completed application received (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/21/2026

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

Balanced Rock Power proposes to construct a 600-megawatt (MW), alternating current (AC) solar photovoltaic (PV) power generating facility with a battery energy storage system (BESS).  The Project’s primary purpose is to produce 600-MW of energy annually.  The Project site would be located in White Pine County, Nevada on approximately 2,891 acres of lands managed by the U.S. Bureau of Land Management (BLM), approximately 15 miles west of Ely, Nevada.  The Project site would be divided into two areas of BLM-managed land adjacent to and on the east and west sides of another proposed solar project.  The Project would also include a 5.8-mile transmission interconnection line at either 500 or 345 kV to interconnect the project to the existing Robinson Summit Substation. 

System Comments
Furthest out
Original Target Date: 10/21/2026
Milestone: Final decision/agency action (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final decision/agency action (Agency Action) extended by 238
From: 10/21/2026
To: 06/16/2027
Approver Comments
BLM committed to adhering to NEPA timeline (with exception of moving milestones for NOI and Scoping) so there is no need to change the ROD milestone
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: