Samantha Solar

PERMITTING DASHBOARD PROJECT POSTING DATE: NOVEMBER 19, 2024

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

Balanced Rock Power proposes to construct a 600-megawatt (MW), alternating current (AC) solar photovoltaic (PV) power generating facility with a battery energy storage system (BESS). The Project’s primary purpose is to produce 600-MW of energy annually.  The Project site would be located in White Pine County, Nevada on approximately 2,891 acres of lands managed by the U.S. Bureau of Land Management (BLM), approximately 15 miles west of Ely, Nevada. The Project site would be divided into two areas of BLM-managed land adjacent to and on the east and west sides of another proposed solar project. The Project would also include a 5.8-mile transmission interconnection line at either 500 or 345 kV to interconnect the project to the existing Robinson Summit Substation. 

Update: 

As requested by the project sponsor and coordinated with the lead agency, the project is paused on the FAST-41 dashboard until February 16, 2027. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete