Permitting Action Modification History

Paused
To ensure the effective administration of public lands, the Bureau of Land Management (BLM) proposes extending the publication of the Notice of Intent in the Federal Register to October 29, 2027. This extension is necessary to provide the project sponsor, Balanced Rock Power, with additional time to engage meaningfully with grazing permittees and address grazing impacts identified during the variance process. The Plan of Development and associated application will need to be revised and resubmitted to reflect these resolutions. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 02-15-2021 02-15-2021 --- Yes
Completed application received (Agency Action) 03-15-2023 03-15-2023 --- Yes
Final decision/agency action (Agency Action) 10-21-2026 10-21-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 02-15-2021 02-15-2021 --- Yes
Completed application received (Agency Action) 03-15-2023 03-15-2023 --- Yes
Final decision/agency action (Agency Action) 10-21-2026 10-21-2026 --- No