The application and supporting documents are filed in the Ely District Office.
None
None
|
Activity |
Public Scoping Meetings: Notice of Intent and public scoping period meetings. One virtual and one in-person meeting will be held during the scoping period |
|
Date |
June to July 2025 |
|
Intended Audience |
All stakeholders |
|
Responsible Party |
Bureau of Land Management |
|
Activity |
Public Meetings: Draft EIS Review Period – one virtual and one in-person meeting will be held during the 90-day public comment period that follows publication of the Draft RMP Amendment/Draft EIS. |
|
Date |
January 2026 |
|
Intended Audience |
All stakeholders |
|
Responsible Party |
Bureau of Land Management |
|
Activity |
Tribal Outreach: BLM will conduct tribal outreach prior to the NOI release, and throughout the NEPA process. |
|
Date |
December 2024 through August 2026 |
|
Intended Audience |
Tribes |
|
Responsible Party |
Bureau of Land Management |
The BLM Variance process for solar energy projects was initially expected to be completed in December 2024. However, with the approval of the 2024 Programmatic Environmental Impact Statement, the variance process has been eliminated.