The Project schedule provided by the proponent accounted for a delivery of a final Plan of Development to the BLM on 4 April 2025 which needed to include a NV
Description:
Environmental Impact Statement with a Resource Management Plan Amendment
Scoping (Agency Action): May to June 2025
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/02/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Description:
Pantheon Solar, LLC proposes to construct, operate, maintain, and eventually decommission a 400-megawatt (MW) solar photovoltaic facility on public lands administered by the U.S. Bureau of Land Management (BLM). The Project’s primary goal is to produce 400-MW of energy annually, which equates to the annual daytime energy needs of approximately 230,000 households. The Project site would encompass approximately 2,682 acres of BLM-administered land located approximately 16 miles west of Ely, Nevada. The Project will include a 500-kilovolt generation tie-line, approximately 6.2 miles in length. Interconnection with the power grid would occur at the Robinson Summit Substation, four miles to the north of the Project site.
Original Target Date: 01/08/2027
Milestone: Issuance of Lead Agency Record of Decision (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Issuance of Lead Agency Record of Decision (Agency Action) extended by 35
From: 01/08/2027
To: 02/12/2027