Milestone Extension: Environmental Impact Statement (EIS)

Submitted by georgeann.smal… on

The Project schedule provided by the proponent accounted for a delivery of a final Plan of Development to the BLM on 4 April 2025 which needed to include a NV IM 2024-01 90-day BLM specialist review. NV IM 2024-019 is a Nevada specific process for all program areas for projects requiring National Environmental Policy Act.  The purpose of the IM is to outline the BLM NV NEPA project management process with greater clarity, incorporate improvements learned over time and include changes to the Council of Environmental Quality’s (CEQ) NEPA regulations Phase 2, which incorporated the 2023 Fiscal Responsibility Act (FRA) (Public Law 118-5 Section 107(f) changes to NEPA.  The project sponsor established the publication for the NOI on 2 May 2025 to begin the Formal NEPA clock. The NV IM requires that the Project provided the Supplemental Information Reports and the Supplemental Environmental Reference (SIRs & SERs) to ensure a thorough review and completeness of the Plan of Development to mitigate delays in the formal NEPA process.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
Planned
POC Name:
Robbie McAboy
POC Title:
District Manager
POC Email:

Description:

Environmental Impact Statement with a Resource Management Plan Amendment

 

Scoping (Agency Action): May to June 2025 

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
  • Monthly Status Report for June 2026:
    The Pantheon Solar Project was paused on June 30, 2026, until the end of the calendar year, at the project sponsor's request. 
  • Monthly Status Report for May 2026:
    The BLM is working in coordination with the project sponsor to update the target dates.
  • Monthly Status Report for April 2026:
    For the effective administration of public lands, the BLM needs to adjust the timeline for the Pantheon Solar Project schedule to allow adequate time to evaluate the project. As such, the review of this project is requiring enhanced coordination that has affected the timeline for this project.
  • Monthly Status Report for March 2026:
    For the effective administration of public lands, the BLM needs to adjust the timeline for the Pantheon Solar Project schedule to allow adequate time to evaluate the project. As such, the review of this project is requiring enhanced coordination that has affected the timeline for this project.
  • Monthly Status Report for February 2026:
    For the effective administration of public lands, the BLM needs to adjust the timeline for the Pantheon Solar Project schedule to allow adequate time to evaluate the project. As such, the review of this project is requiring enhanced coordination that has affected the timeline for this project.
  • Monthly Status Report for January 2026:
    For the effective administration of public lands, the BLM needs to adjust the timeline for the Pantheon Solar Project schedule to allow adequate time to evaluate the project. As such, the review of this project is requiring enhanced coordination that has affected the timeline for this project.
  • Monthly Status Report for December 2025:
    For the effective administration of public lands, the BLM needs to adjust the timeline for the Pantheon Solar Project schedule to allow adequate time to evaluate the project. As such, the review of this project is requiring enhanced coordination that has affected the timeline for this project.
  • Monthly Status Report for November 2025:
    For the effective administration of public lands, the BLM needs to adjust the timeline for the Pantheon Solar Project schedule to allow adequate time to evaluate the project. As such, the review of this project is requiring enhanced coordination that has affected the timeline for this project.
  • Monthly Status Report for October 2025:
    The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. BLM is working towards meeting required enhanced coordination and reviews.
  • Monthly Status Report for September 2025:
    The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. BLM is working towards meeting required enhanced coordination and reviews.
  • Monthly Status Report for August 2025:
    The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
  • Monthly Status Report for July 2025:
    The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
  • Non-conformance Explanation:
    The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. 
Current Target Date:
Scoping (Agency Action)
Current Target Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

Pantheon Solar, LLC proposes to construct, operate, maintain, and eventually decommission a 400-megawatt (MW) solar photovoltaic facility on public lands administered by the U.S. Bureau of Land Management (BLM).  The Project’s primary goal is to produce 400-MW of energy annually, which equates to the annual daytime energy needs of approximately 230,000 households.  The Project site would encompass approximately 2,682 acres of BLM-administered land located approximately 16 miles west of Ely, Nevada.  The Project will include a 500-kilovolt generation tie-line, approximately 6.2 miles in length. Interconnection with the power grid would occur at the Robinson Summit Substation, four miles to the north of the Project site. 

field_status
System Comments
Furthest out
Original Target Date: 01/08/2027
Milestone: Issuance of Lead Agency Record of Decision (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Lead Agency Record of Decision (Agency Action) extended by 35
From: 01/08/2027
To: 02/12/2027
Approver Comments
EDD signed April 14, 2025 granting the milestone changes
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: