Alaska LNG Project
PERMITTING DASHBOARD PROJECT POSTING DATE: AUGUST 22, 2017PROJECT WEBSITE: http://alaska-lng.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/05/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of Homeland Security, US Coast Guard
Department of the Interior, Bureau of Land Management
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Energy, Office of Fossil Energy
Department of the Interior, National Park Service
Department of Energy
Description:
The proposed Alaska LNG Project is comprised of the following integrated and interdependent facilities: an LNG terminal in Southcentral Alaska designed to produce up to 20 million metric tons per annum of LNG; an approximately 807-mile, 42-inch diameter gas pipeline; a gas treatment plant (GTP) within the Prudhoe Bay Unit (PBU) on the North Slope; an approximately 1-mile, 60-inch diameter gas transmission line connecting the GTP to the PBU gas production facility; and an approximately 63-mile, 32-inch diameter gas transmission line connecting the GTP to the Point Thomson gas production facility. The mainline of the Alaska LNG Project would traverse over 800 miles from the GTP on the North Slope of Alaska through several boroughs before it crosses Cook Inlet and connects with the liquefaction plant and marine terminal in Nikiski, Alaska.
The project was initially determined to be a FAST-41 covered project in 2017. As represented in the permitting timetable, the federal environmental review and authorization process for the project was originally completed in 2020, and the project was marked as complete on the Permitting Dashboard. After the Department of Energy (DOE) granted a request for rehearing of a final order in 2021, the project was reopened on the Permitting Dashboard to include DOE’s preparation of a supplemental Environmental Impact Statement (EIS). Following the issuance of the supplemental EIS, DOE issued an updated order, and the project was marked as complete on the Permitting Dashboard in 2023.
On February 26, 2025, the project sponsor submitted a notice seeking to reinitiate FAST-41 coverage for updated Biological Opinions (under the Endangered Species Act) and renewed authorizations that are needed for the project. On March 12, 2025, it was determined that the project continues to qualify for FAST-41 coverage. Corresponding updates to the permitting timetable were posted on May 9, 2025.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|