Permitting Action Modification History

Complete
DOE completed this action on 4/13/23. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 07-02-2021 07-02-2021 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 05-02-2022 06-29-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 09-15-2022 01-11-2023 --- Yes
Supplemental EIS process concluded (Agency Action) 12-14-2022 03-30-2023 04-13-2023 Yes
In Progress
Due to the range of issues addressed in the Final SEIS, DOE has determined that it will need no more than 21 days to complete the Final Order and NEPA Record of Decision. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 07-02-2021 07-02-2021 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 05-02-2022 06-29-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 09-15-2022 01-11-2023 --- Yes
Supplemental EIS process concluded (Agency Action) 12-14-2022 03-30-2023 04-20-2023 No
In Progress
DOE completed the FEIS prior to the milestone date so updating dashboard accordingly.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 07-02-2021 07-02-2021 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 05-02-2022 06-29-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 09-15-2022 01-11-2023 --- Yes
Supplemental EIS process concluded (Agency Action) 12-14-2022 03-30-2023 --- No
In Progress
DOE received more than 200 public comments on the draft SEIS. Due to both the complexity of the comments and the range of issues addressed by the commenters, it has been necessary for DOE and NETL to consider additional technical analysis. Accordingly, DOE provided a Second Notice of Amended Schedule. DOE extended the date to publish the final order and NEPA Record of Decision by 45 days. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 07-02-2021 07-02-2021 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 05-02-2022 06-29-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 09-15-2022 01-13-2023 --- No
Supplemental EIS process concluded (Agency Action) 12-14-2022 03-30-2023 --- No
In Progress
DOE received more than 200 public comments on the draft SEIS. Due to both the complexity of the comments and the range of issues addressed by the commenters, it has been necessary for DOE and NETL to consider additional technical analysis. Accordingly, DOE is providing notice of a second amended SEIS schedule. DOE has determined that it will need an additional 60 days to complete the technical review and the development of responses for the final SEIS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 07-02-2021 07-02-2021 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 05-02-2022 06-29-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 09-15-2022 01-13-2023 --- No
Supplemental EIS process concluded (Agency Action) 12-14-2022 02-13-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 07-02-2021 07-02-2021 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 05-02-2022 06-29-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 09-15-2022 11-14-2022 --- No
Supplemental EIS process concluded (Agency Action) 12-14-2022 02-13-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 07-02-2021 07-02-2021 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 05-02-2022 07-01-2022 --- No
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 09-15-2022 11-14-2022 --- No
Supplemental EIS process concluded (Agency Action) 12-14-2022 02-13-2023 --- No