USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Section 408 Permit: Completeness Determination (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 03/09/2026 for Completeness Determination (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Jaeson Hall

Description:

Section 408 - USACE Vicksburg District for Yazoo River Crossing

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Completeness Determination (Agency Action)
Current Target Date:
Complete application submitted (Applicant Action)
Current Target Date:
Issuance of Decision (Agency Action)
Current Target Date:
Milestone
Completeness Determination (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Mississippi Crossing Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/07/2026

0 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, National Park Service

No icon

Department of Defense, US Army Corps of Engineers - Civil Works

Description:

The proposed project would consist of approximately 199 miles of new 36-inch and 42-inch-diameter pipeline extending southeast from an interconnection near Greenville, Mississippi, to Butler, Alabama. Additional facilities would include approximately seven miles of new 36-inch diameter pipeline (the CGT Lateral) in Humphreys and Sunflower Counties, Mississippi, and approximately two miles of new 30-inch and 36-inch-diameter laterals interconnecting with third-party pipelines in Attala and Lauderdale Counties, Mississippi, and Choctaw County, Alabama. Three new compressor stations would be constructed along the Mississippi Crossing Pipeline in Humphreys, Attala, and Lauderdale Counties, with modifications at one existing compressor station in Washington County. The proposed project would also include construction of four new meter stations to accommodate interconnections with other pipeline systems, three overpressure protection facilities with clamp-on meters at key interconnections, and additional appurtenant and auxiliary facilities. The proposed project would provide 2.1 billion cubic feet per day of incremental firm natural gas transportation capacity for markets in the Southeast.

field_status
System Comments
Agency Milestone Date of 03/09/2026 for Completeness Determination (Agency Action) has passed by 1 business days
Approver Comments
Agency completed milestone on time
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Completeness Determination (Agency Action)
Current Target Date:
Response Date