USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Mississippi Crossing Project

PERMITTING DASHBOARD PROJECT POSTING DATE: NOVEMBER 05, 2025

PROJECT WEBSITE: Mississippi Crossing Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/07/2026

0 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, National Park Service

Description:

The proposed project would consist of approximately 199 miles of new 36-inch and 42-inch-diameter pipeline extending southeast from an interconnection near Greenville, Mississippi, to Butler, Alabama. Additional facilities would include approximately seven miles of new 36-inch diameter pipeline (the CGT Lateral) in Humphreys and Sunflower Counties, Mississippi, and approximately two miles of new 30-inch and 36-inch-diameter laterals interconnecting with third-party pipelines in Attala and Lauderdale Counties, Mississippi, and Choctaw County, Alabama. Three new compressor stations would be constructed along the Mississippi Crossing Pipeline in Humphreys, Attala, and Lauderdale Counties, with modifications at one existing compressor station in Washington County. The proposed project would also include construction of four new meter stations to accommodate interconnections with other pipeline systems, three overpressure protection facilities with clamp-on meters at key interconnections, and additional appurtenant and auxiliary facilities. The proposed project would provide 2.1 billion cubic feet per day of incremental firm natural gas transportation capacity for markets in the Southeast.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete