Mississippi Crossing Project
PERMITTING DASHBOARD PROJECT POSTING DATE: NOVEMBER 05, 2025PROJECT WEBSITE: Mississippi Crossing Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/07/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Department of the Interior, National Park Service
Description:
The proposed project would consist of approximately 199 miles of new 36-inch and 42-inch-diameter pipeline extending southeast from an interconnection near Greenville, Mississippi, to Butler, Alabama. Additional facilities would include approximately seven miles of new 36-inch diameter pipeline (the CGT Lateral) in Humphreys and Sunflower Counties, Mississippi, and approximately two miles of new 30-inch and 36-inch-diameter laterals interconnecting with third-party pipelines in Attala and Lauderdale Counties, Mississippi, and Choctaw County, Alabama. Three new compressor stations would be constructed along the Mississippi Crossing Pipeline in Humphreys, Attala, and Lauderdale Counties, with modifications at one existing compressor station in Washington County. The proposed project would also include construction of four new meter stations to accommodate interconnections with other pipeline systems, three overpressure protection facilities with clamp-on meters at key interconnections, and additional appurtenant and auxiliary facilities. The proposed project would provide 2.1 billion cubic feet per day of incremental firm natural gas transportation capacity for markets in the Southeast.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|