The project sponsor filed an application under section 7 of the Natural Gas Act on June 30, 2025. The application and other supporting documents can be found under docket number CP25-514 in the Commission's eLibrary system.
On July 31, 2026, the Commission issued an order authorizing the project, subject to certain environmental conditions.
There is no active litigation on the Commission's certificate proceeding.
Information on the timing of project-related comment periods and public meetings will be added to this section as it becomes available.
- On July 15, 2025, the Commission issued a notice with information on how to become involved in the Commission's review process, including filing comments.
- On September 5, 2025, the Commission issued a notice establishing a deadline for filing comments on the scope of issues to address in the Environmental Impact Statement.
- On January 30, 2026, the Commission issued a notice with information on submitting written comments and attending public comment sessions on the draft Environmental Impact Statement.
- On July 15, 2025, the Commission issued a Notice of Applications.
- On September 5, 2025, the Commission issued a Notice of Intent to Prepare an Environmental Impact Statement.
- On December 31, 2025, the Commission issued a Notice of Schedule for the Final Order.
- On January 30, 2026, the Commission issued a draft Environmental Impact Statement.
- On June 26, 2026, the Commission issued a final Environmental Impact Statement.
- On July 31, 2026, the Commission issued an order authorizing the project.