Permitting Action Modification History
Modifications on 05/18/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-09-2026 | 02-09-2026 | --- | Yes |
| Completeness Determination (Agency Action) | 03-09-2026 | 03-09-2026 | --- | Yes |
| Complete application submitted (Applicant Action) | 06-01-2026 | 04-20-2026 | --- | Yes |
| Issuance of Decision (Agency Action) | 09-01-2026 | 05-05-2026 | --- | Yes |
Modifications on 03/11/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-09-2026 | 02-09-2026 | --- | Yes |
| Completeness Determination (Agency Action) | 03-09-2026 | 03-09-2026 | --- | Yes |
| Complete application submitted (Applicant Action) | 06-01-2026 | 06-01-2026 | --- | No |
| Issuance of Decision (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |
Modifications on 02/12/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-09-2026 | 02-09-2026 | --- | Yes |
| Completeness Determination (Agency Action) | 03-09-2026 | 03-09-2026 | --- | No |
| Complete application submitted (Applicant Action) | 06-01-2026 | 06-01-2026 | --- | No |
| Issuance of Decision (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |
Modifications on 01/26/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-09-2026 | 02-09-2026 | --- | No |
| Completeness Determination (Agency Action) | 03-09-2026 | 03-09-2026 | --- | No |
| Complete application submitted (Applicant Action) | 06-01-2026 | 06-01-2026 | --- | No |
| Issuance of Decision (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |