Triggered missed date from extending Section 106 consultation concluded (Agency Action) within 30 days of its current target date which was 06/21/2024 and extended to 08/21/2024
Milestones:
-
Monthly Status Report for July 2024:BOEM distributed the MOA for signature on July 31 and is on track to meet the alternative completion date milestone of Aug 21, to conclude Section 106 consultation.
-
Monthly Status Report for June 2024:The Historic Property Treatment Plans (HPTPs) were received from the sponsor on March 27, 2024, which delayed consultations with Tribal nations and the Delaware SHPO about terrestrial archaeology mitigations and HPTPs. Those consultations are underway with a clear path forward but were unlikely to be completed in compliance with the FAST-41 schedule. Finalization of the MOA is required prior to ROD issuance. The alternative milestone shifts the milestone by 60-days to allow for completion of consultations within a timeline that is still well prior to ROD issuance, as required.
-
Non-conformance Explanation:The Historic Property Treatment Plans (HPTPs) were received from the sponsor on March 27, 2024, instead of March 1 as anticipated, which delayed consultations with Tribal nations and the Delaware SHPO about terrestrial archaeology mitigations and HPTPs. Those consultations are underway with a clear path forward but were unlikely to be completed in compliance with the FAST-41 schedule. Finalization of the MOA is required prior to ROD issuance. The alternative milestone shifts the milestone by 60-days to allow for completion of consultations within a timeline that is still well prior to ROD issuance, as required.
-
Monthly Status Report for July 2024:BOEM distributed the MOA for signature on July 31 and is on track to meet the alternative completion date milestone of Aug 21, to conclude Section 106 consultation.
-
Monthly Status Report for June 2024:The Historic Property Treatment Plans (HPTPs) were received from the sponsor on March 27, 2024, which delayed consultations with Tribal nations and the Delaware SHPO about terrestrial archaeology mitigations and HPTPs. Those consultations are underway with a clear path forward but were unlikely to be completed in compliance with the FAST-41 schedule. Finalization of the MOA is required prior to ROD issuance. The alternative milestone shifts the milestone by 60-days to allow for completion of consultations within a timeline that is still well prior to ROD issuance, as required.
-
Non-conformance Explanation:The Historic Property Treatment Plans (HPTPs) were received from the sponsor on March 27, 2024, instead of March 1 as anticipated, which delayed consultations with Tribal nations and the Delaware SHPO about terrestrial archaeology mitigations and HPTPs. Those consultations are underway with a clear path forward but were unlikely to be completed in compliance with the FAST-41 schedule. Finalization of the MOA is required prior to ROD issuance. The alternative milestone shifts the milestone by 60-days to allow for completion of consultations within a timeline that is still well prior to ROD issuance, as required.
PROJECT WEBSITE: http://www.uswindinc.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/03/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Description:
US Wind is proposing the development and eventual decommissioning of the Maryland Offshore Wind Project, an offshore wind energy project (including an Operations and Maintenance Facility) of up to approximately 2 gigawatts of nameplate capacity within OCS-A 0490 (the Lease). The Lease area covers 79,707 acres with the western edge located approximately 18.5 km (11.5 miles) off the coast of Maryland on the Outer Continental Shelf.
Update:
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the COP, Section 106, MMPA, Section 10/404, and Section 408 actions completion date on August 17, 2023. The Executive Director determination is posted here.
-
Monthly Status Report for July 2024:BOEM distributed the MOA for signature on July 31 and is on track to meet the alternative completion date milestone of Aug 21, to conclude Section 106 consultation.
-
Monthly Status Report for June 2024:The Historic Property Treatment Plans (HPTPs) were received from the sponsor on March 27, 2024, which delayed consultations with Tribal nations and the Delaware SHPO about terrestrial archaeology mitigations and HPTPs. Those consultations are underway with a clear path forward but were unlikely to be completed in compliance with the FAST-41 schedule. Finalization of the MOA is required prior to ROD issuance. The alternative milestone shifts the milestone by 60-days to allow for completion of consultations within a timeline that is still well prior to ROD issuance, as required.
-
Non-conformance Explanation:The Historic Property Treatment Plans (HPTPs) were received from the sponsor on March 27, 2024, instead of March 1 as anticipated, which delayed consultations with Tribal nations and the Delaware SHPO about terrestrial archaeology mitigations and HPTPs. Those consultations are underway with a clear path forward but were unlikely to be completed in compliance with the FAST-41 schedule. Finalization of the MOA is required prior to ROD issuance. The alternative milestone shifts the milestone by 60-days to allow for completion of consultations within a timeline that is still well prior to ROD issuance, as required.