Agency Milestone Date of 08/16/2024 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Nevada
Milestones:
-
Monthly Status Report for March 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for February 2025:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is complete.
-
Monthly Status Report for January 2025:Section 106 Review was initiated on October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2024:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for November 2024:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for October 2024:Initiation of Section 106 was completed on October 4, 2024, seven days ahead of the planned date.
-
Monthly Status Report for September 2024:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM reviewed the revised report and provided minimal comments back on 9/24/2024 and requested hard copies of the documents for SHPO/THPO consultation. BLM verified the report was complete on 9/26/2024 and will begin work on preparation of SHPO/THPO consultation initiation documents. The BLM plans to initiate SHPO/THPO consultation by October 11, 2024. This shifts the alternative milestone date by 15 days to allow for preparation and transmittal of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
-
Non-conformance Explanation:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM needs adequate time for review of the revised documents to verify completeness, as well as preparation of SHPO/THPO consultation initiation documents. Pending any additional changes or requirements, the BLM plans to initiate SHPO/THPO consultation by September 26, 2024. This shifts the milestone by 41 days to allow for review and preparation of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
-
Monthly Status Report for March 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for February 2025:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is complete.
-
Monthly Status Report for January 2025:Section 106 Review was initiated on October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2024:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for November 2024:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for October 2024:Initiation of Section 106 was completed on October 4, 2024, seven days ahead of the planned date.
-
Monthly Status Report for September 2024:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM reviewed the revised report and provided minimal comments back on 9/24/2024 and requested hard copies of the documents for SHPO/THPO consultation. BLM verified the report was complete on 9/26/2024 and will begin work on preparation of SHPO/THPO consultation initiation documents. The BLM plans to initiate SHPO/THPO consultation by October 11, 2024. This shifts the alternative milestone date by 15 days to allow for preparation and transmittal of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
-
Non-conformance Explanation:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM needs adequate time for review of the revised documents to verify completeness, as well as preparation of SHPO/THPO consultation initiation documents. Pending any additional changes or requirements, the BLM plans to initiate SHPO/THPO consultation by September 26, 2024. This shifts the milestone by 41 days to allow for review and preparation of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
The Silver Star Solar 1 (project) would be entirely on land administered by the Bureau of Land Management (BLM), Southern Nevada District Office (SNDO) in the unincorporated Town of Amargosa Valley, Nye County, Nevada. The proposed project includes construction, operation, maintenance, and decommissioning of a 650 megawatt (MW) alternating current solar photovoltaic power generating facility with a 650 MW battery energy storage system on approximately 3,005 acres. The solar generation field would be located approximately five miles south of U.S. Highway 95 and six miles west of State Highway 373. Death Valley National Park is approximately four miles southwest of the Project. The proposed Project would be on Solar Variance lands as identified in the 2012 Final Programmatic Environmental Impact Statement for Solar Energy Development in Six Southwestern States (Solar PEIS).
The Executive Director granted a Bureau of Land Management request to extend the Right-of-Way Authorization, NEPA, and ESA-FWS completion dates on December 20, 2024. The Executive Director determination is posted here.
-
Monthly Status Report for March 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for February 2025:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is complete.
-
Monthly Status Report for January 2025:Section 106 Review was initiated on October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2024:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for November 2024:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for October 2024:Initiation of Section 106 was completed on October 4, 2024, seven days ahead of the planned date.
-
Monthly Status Report for September 2024:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM reviewed the revised report and provided minimal comments back on 9/24/2024 and requested hard copies of the documents for SHPO/THPO consultation. BLM verified the report was complete on 9/26/2024 and will begin work on preparation of SHPO/THPO consultation initiation documents. The BLM plans to initiate SHPO/THPO consultation by October 11, 2024. This shifts the alternative milestone date by 15 days to allow for preparation and transmittal of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
-
Non-conformance Explanation:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM needs adequate time for review of the revised documents to verify completeness, as well as preparation of SHPO/THPO consultation initiation documents. Pending any additional changes or requirements, the BLM plans to initiate SHPO/THPO consultation by September 26, 2024. This shifts the milestone by 41 days to allow for review and preparation of documents, this shift is anticipated to not affect the consultation conclusion milestone date.