Agency Milestone Date of 08/16/2024 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Nevada
Milestones:
-
Monthly Status Report for September 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is taking place with the required consulting parties and will continue through the end of the NEPA Analysis for the project. Completion of Section 106 is on schedule to meet current established target of December of 2027.
-
Monthly Status Report for August 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is taking place with the required consulting parties and will continue through the end of the NEPA Analysis for the project. Completion of Section 106 is on schedule to meet current established target of December of 2027.
-
Monthly Status Report for July 2026:The Section 106 Reviews commenced on October 4, 2024. Consultations had been postponed as a result of internal evaluations and delays related to baseline studies required for NEPA. Completion of the Section 106 Consultation is anticipated in December of 2027.
-
Monthly Status Report for June 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation will continue through the end of the project.
-
Monthly Status Report for May 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation will continue through the end of the project.
-
Monthly Status Report for April 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for March 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for February 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for January 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2025:Initiation of Section 106 Review was initiated October 4, 2024. The Bureau of Land Management (BLM) requested to extend the target dates related to the Environmental Assessment (EA) which would affect the completion dates for the Section 106 review. This request was approved on 11/31/2025. BLM will continue to consult with the with SHPO/THPO until the final EA is expected to be issued.
-
Monthly Status Report for November 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued. On October 27, 2025, BLM submitted a request to extend the timeline, which was approved on November 13, 2025.
-
Monthly Status Report for October 2025:The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. BLM is working towards meeting required enhanced coordination and reviews. Consultation would resume if approved by DOI
-
Monthly Status Report for September 2025:Consultation continues and will conclude when the final environmental assessment is expected to be issued (in December of 2026).
-
Monthly Status Report for August 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for July 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for June 2025:Initiation of Section 106 Review was initiated October 4, 2024. On June 20, 2025, an EDD request was submitted to move the final environmental assessment milestone target date to November 16, 2026. This request is expected to be approved. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for May 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for April 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for March 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for February 2025:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is complete.
-
Monthly Status Report for January 2025:Section 106 Review was initiated on October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2024:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for November 2024:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for October 2024:Initiation of Section 106 was completed on October 4, 2024, seven days ahead of the planned date.
-
Monthly Status Report for September 2024:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM reviewed the revised report and provided minimal comments back on 9/24/2024 and requested hard copies of the documents for SHPO/THPO consultation. BLM verified the report was complete on 9/26/2024 and will begin work on preparation of SHPO/THPO consultation initiation documents. The BLM plans to initiate SHPO/THPO consultation by October 11, 2024. This shifts the alternative milestone date by 15 days to allow for preparation and transmittal of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
-
Non-conformance Explanation:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM needs adequate time for review of the revised documents to verify completeness, as well as preparation of SHPO/THPO consultation initiation documents. Pending any additional changes or requirements, the BLM plans to initiate SHPO/THPO consultation by September 26, 2024. This shifts the milestone by 41 days to allow for review and preparation of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
-
Monthly Status Report for September 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is taking place with the required consulting parties and will continue through the end of the NEPA Analysis for the project. Completion of Section 106 is on schedule to meet current established target of December of 2027.
-
Monthly Status Report for August 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is taking place with the required consulting parties and will continue through the end of the NEPA Analysis for the project. Completion of Section 106 is on schedule to meet current established target of December of 2027.
-
Monthly Status Report for July 2026:The Section 106 Reviews commenced on October 4, 2024. Consultations had been postponed as a result of internal evaluations and delays related to baseline studies required for NEPA. Completion of the Section 106 Consultation is anticipated in December of 2027.
-
Monthly Status Report for June 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation will continue through the end of the project.
-
Monthly Status Report for May 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation will continue through the end of the project.
-
Monthly Status Report for April 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for March 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for February 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for January 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2025:Initiation of Section 106 Review was initiated October 4, 2024. The Bureau of Land Management (BLM) requested to extend the target dates related to the Environmental Assessment (EA) which would affect the completion dates for the Section 106 review. This request was approved on 11/31/2025. BLM will continue to consult with the with SHPO/THPO until the final EA is expected to be issued.
-
Monthly Status Report for November 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued. On October 27, 2025, BLM submitted a request to extend the timeline, which was approved on November 13, 2025.
-
Monthly Status Report for October 2025:The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. BLM is working towards meeting required enhanced coordination and reviews. Consultation would resume if approved by DOI
-
Monthly Status Report for September 2025:Consultation continues and will conclude when the final environmental assessment is expected to be issued (in December of 2026).
-
Monthly Status Report for August 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for July 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for June 2025:Initiation of Section 106 Review was initiated October 4, 2024. On June 20, 2025, an EDD request was submitted to move the final environmental assessment milestone target date to November 16, 2026. This request is expected to be approved. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for May 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for April 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for March 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for February 2025:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is complete.
-
Monthly Status Report for January 2025:Section 106 Review was initiated on October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2024:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for November 2024:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for October 2024:Initiation of Section 106 was completed on October 4, 2024, seven days ahead of the planned date.
-
Monthly Status Report for September 2024:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM reviewed the revised report and provided minimal comments back on 9/24/2024 and requested hard copies of the documents for SHPO/THPO consultation. BLM verified the report was complete on 9/26/2024 and will begin work on preparation of SHPO/THPO consultation initiation documents. The BLM plans to initiate SHPO/THPO consultation by October 11, 2024. This shifts the alternative milestone date by 15 days to allow for preparation and transmittal of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
-
Non-conformance Explanation:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM needs adequate time for review of the revised documents to verify completeness, as well as preparation of SHPO/THPO consultation initiation documents. Pending any additional changes or requirements, the BLM plans to initiate SHPO/THPO consultation by September 26, 2024. This shifts the milestone by 41 days to allow for review and preparation of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/06/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
The Silver Star Solar 1 (project) would be entirely on land administered by the Bureau of Land Management (BLM), Southern Nevada District Office (SNDO) in the unincorporated Town of Amargosa Valley, Nye County, Nevada. The proposed project includes construction, operation, maintenance, and decommissioning of a 650 megawatt (MW) alternating current solar photovoltaic power generating facility with a 650 MW battery energy storage system on approximately 3,005 acres. The solar generation field would be located approximately five miles south of U.S. Highway 95 and six miles west of State Highway 373. Death Valley National Park is approximately four miles southwest of the Project. The proposed Project would be on Solar Variance lands as identified in the 2012 Final Programmatic Environmental Impact Statement for Solar Energy Development in Six Southwestern States (Solar PEIS).
The Executive Director granted a Bureau of Land Management request to extend the Right-of-Way Authorization, NEPA, and ESA-FWS completion dates on December 20, 2024. The Executive Director determination is posted here.
a {
text-decoration: none;
color: #464feb;
}
tr th, tr td {
border: 1px solid #e6e6e6;
}
tr th {
background-color: #f5f5f5;
}
</style></p><div style="font-family:'Segoe UI';font-size:14px;font-style:normal;font-weight:400;line-height:20px;"><p>Due to deficiencies identified in the Cultural Resources Report, the report was returned to the applicant's contractor for revision. The BLM Nevada State Office is currently working with the applicant and the contractor to determine when the revised draft will be submitted, which will provide greater clarity regarding the timeline for making a determination.</p><p>Given the significant findings identified during the cultural resources inventory associated with this project, the BLM acceptance of the report will be critical to supporting the determination process and facilitating ongoing consultation with the Nevada SHPO and affected Native American Tribal Nations.</p></div>
-
Monthly Status Report for September 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is taking place with the required consulting parties and will continue through the end of the NEPA Analysis for the project. Completion of Section 106 is on schedule to meet current established target of December of 2027.
-
Monthly Status Report for August 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is taking place with the required consulting parties and will continue through the end of the NEPA Analysis for the project. Completion of Section 106 is on schedule to meet current established target of December of 2027.
-
Monthly Status Report for July 2026:The Section 106 Reviews commenced on October 4, 2024. Consultations had been postponed as a result of internal evaluations and delays related to baseline studies required for NEPA. Completion of the Section 106 Consultation is anticipated in December of 2027.
-
Monthly Status Report for June 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation will continue through the end of the project.
-
Monthly Status Report for May 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation will continue through the end of the project.
-
Monthly Status Report for April 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for March 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for February 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation is ongoing.
-
Monthly Status Report for January 2026:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2025:Initiation of Section 106 Review was initiated October 4, 2024. The Bureau of Land Management (BLM) requested to extend the target dates related to the Environmental Assessment (EA) which would affect the completion dates for the Section 106 review. This request was approved on 11/31/2025. BLM will continue to consult with the with SHPO/THPO until the final EA is expected to be issued.
-
Monthly Status Report for November 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued. On October 27, 2025, BLM submitted a request to extend the timeline, which was approved on November 13, 2025.
-
Monthly Status Report for October 2025:The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. BLM is working towards meeting required enhanced coordination and reviews. Consultation would resume if approved by DOI
-
Monthly Status Report for September 2025:Consultation continues and will conclude when the final environmental assessment is expected to be issued (in December of 2026).
-
Monthly Status Report for August 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for July 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for June 2025:Initiation of Section 106 Review was initiated October 4, 2024. On June 20, 2025, an EDD request was submitted to move the final environmental assessment milestone target date to November 16, 2026. This request is expected to be approved. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for May 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for April 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for March 2025:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for February 2025:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is complete.
-
Monthly Status Report for January 2025:Section 106 Review was initiated on October 4, 2024. Consultation with SHPO/THPO is ongoing and will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for December 2024:Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for November 2024:Initiation of Section 106 Review was initiated October 4, 2024. Consultation with SHPO/THPO will continue until the final environmental assessment is expected to be issued.
-
Monthly Status Report for October 2024:Initiation of Section 106 was completed on October 4, 2024, seven days ahead of the planned date.
-
Monthly Status Report for September 2024:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM reviewed the revised report and provided minimal comments back on 9/24/2024 and requested hard copies of the documents for SHPO/THPO consultation. BLM verified the report was complete on 9/26/2024 and will begin work on preparation of SHPO/THPO consultation initiation documents. The BLM plans to initiate SHPO/THPO consultation by October 11, 2024. This shifts the alternative milestone date by 15 days to allow for preparation and transmittal of documents, this shift is anticipated to not affect the consultation conclusion milestone date.
-
Non-conformance Explanation:The Project Sponsor submitted the required Cultural Class I Inventory and Work Plan on 6/28/2024. BLM reviewed the information and provided comments on 7/25/2024. The Project Sponsor provided the revised documents addressing BLM comments on 8/12/2024. BLM needs adequate time for review of the revised documents to verify completeness, as well as preparation of SHPO/THPO consultation initiation documents. Pending any additional changes or requirements, the BLM plans to initiate SHPO/THPO consultation by September 26, 2024. This shifts the milestone by 41 days to allow for review and preparation of documents, this shift is anticipated to not affect the consultation conclusion milestone date.