Permitting Action Modification History

In Progress
As part of BLM’s effort to align with the Department of the Interior’s July 15, 2025 memorandum, updates to the Project schedule, including updating the milestone dates on the FAST-41 Dashboard, are necessary to comply with the new requirement that all wind and solar energy project decisions, actions, consultations, and other undertakings be routed through the Office of the Secretary for final review prior to the agency taking action. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 08-16-2024 10-04-2024 Yes
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 12-06-2027 No
In Progress
BLM’s justification for this permitting timetable extension is to account for the additional time needed for the Project Sponsor to complete the cultural and golden and bald eagle surveys and BLM to subsequently review the Project Sponsor’s submissions, BLM is requesting an extension of approximately six months for issuance of the final NEPA document and the right-of-way authorization. The final completion dates for the Section 106 consultation are dependent on the NEPA action. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 08-16-2024 10-04-2024 Yes
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 11-15-2026 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 08-16-2024 10-04-2024 Yes
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 05-08-2026 No
In Progress
BLM, as part of its standard process for solar projects, requires several baseline studies before beginning NEPA. The Project Sponsor and BLM have worked together to ensure completeness of the required studies and coordinated to manage BLM review and Project Sponsor submittals to maintain progress. Through recent increased coordination, the agency and Project Sponsor agreed that additional time is needed to finalize and approve the required studies. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 08-16-2024 10-04-2024 Yes
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 05-08-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 08-16-2024 10-04-2024 Yes
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 --- No
Planned
The Project Sponsor provided revised documents addressing BLM comments on 8/12/2024. BLM reviewed the revised report and provided minimal comments back on 9/24/2024 and requested hard copies of the documents for SHPO/THPO consultation. BLM verified the report was complete on 9/26/2024 and will begin work on preparation of SHPO/THPO consultation initiation documents. The BLM plans to initiate SHPO/THPO consultation by October 11, 2024. This shifts the milestone by 15 days to allow for preparation and transmittal of documents.  This shift is anticipated to not affect the consultation conclusion milestone date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 08-16-2024 10-11-2024 No
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 --- No
Planned
Alternative milestone date for SHPO/THPO consultation initiation resulting from nonconformance. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 08-16-2024 09-26-2024 No
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 --- No
Planned
The Applicant stated they will submit the required information on 6/28/2024 to BLM for SHPO/THPO consultation. BLM needs time to review and verify the information is complete. BLM may be able to initiate consultation earlier than 8/16/2024, however BLM needs adequate time for review. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 08-16-2024 --- No
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 --- No
Planned
Project sponsor has not yet submitted the cultural/historic information because they had to change contractors. Original submission date for the information was May 20, 2024. BLM requires the information prior to initiation of SHPO/THPO consultation. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 07-30-2024 --- No
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2024 06-30-2024 --- No
Section 106 consultation concluded (Agency Action) 10-30-2025 10-30-2025 --- No