FAST-41 Postings by Agencies for Mountain Valley and Equitrans Expansion Project

Federal Energy Regulatory Commission (Posted on: )

Application and Supporting Documents

The project sponsor filed an application pursuant to section 7(c) of the Natural Gas Act for a certificate of public convenience and necessity on October 23, 2015. And the project sponsor filed an application to amend its certificate of public convenience and necessity on February 19, 2021. The applications and other supporting documents can be found by searching under docket numbers CP16-10 and CP21-57 in the Commission’s eLibrary system.   

Information on the status of mitigation measures

The Commission issued a certificate and an amended certificate for the project on October 13, 2017, and April 8, 2022, respectively. These orders include appendices specifying environmental conditions, including mitigation measures. The project sponsor has implemented the required environmental conditions to commence project construction. 

Description of the status of any litigation

There is no active litigation on the Commission’s certificate proceedings.

Information about project-related public meetings, public hearings, and public comment periods

The Commission has no planned public meetings, public hearings, or public comment periods. 

Description of any Federal agency action taken or decision made that materially affects the status of the project

The Commission issued a certificate and an amended certificate for the project on October 13, 2017, and April 8, 2022, respectively. Commission staff issued National Environmental Policy Act documents prior to the Commission’s issuance of the certificate and amended certificate for the project, including a Final Environmental Impact Statement under CP16-10 and an Environmental Assessment under CP21-57.

Bureau of Land Management (Posted on: )

FAST-41 Initiation Notice

FAST-41 Initiation September 22, 2016, completed December 28, 2017

2nd FAST-41 Initiation September 1, 2022, completed May 17, 2023

https://www.mountainvalleypipeline.info

Application and Supporting Documents

Initial application received April 6, 2017, completed March 3, 2017

2nd initial application received August 5, 2022, completed September 1, 2023

https://www.mountainvalleypipeline.info

Information on the status of mitigation measures
Description of the status of any litigation
Information about project-related public meetings, public hearings, and public comment periods
Description of any Federal agency action taken or decision made that materially affects the status of the project