Mountain Valley and Equitrans Expansion Project
PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016PROJECT WEBSITE: https://www.mountainvalleypipeline.info/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/23/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, National Park Service
Department of the Interior, Bureau of Land Management
Department of Agriculture, US Forest Service
Description:
On August 18, 2022, Mountain Valley Pipeline, LLC submitted a FAST-41 Initiation Notice for the outstanding federal environmental reviews and authorizations for the project following associated court decisions. A determination of FAST-41 coverage was made on September 1, 2022.
The project was previously in the initial inventory of FAST-41 covered projects designated by the Executive Director of the Federal Permitting Improvement Steering Council in September 2016 before being closed out on the Permitting Dashboard in late 2017.
As described in the project sponsor’s FAST-41 Initiation Notice, the project includes the construction of approximately 304 miles of natural gas pipeline in West Virginia and Virginia, three new compressor stations in West Virginia, metering stations, taps, and appurtenant facilities. The project would provide up to 2,000,000 dekatherms per day of firm natural gas transportation service from northern West Virginia to southwestern Virginia.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|