USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Right-of-Way Authorization (DOI-BLM): Completed application received (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 11/17/2025 for Completed application received (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Lea Garcia
POC Title:
Energy Development Project Manager
POC Email:

Milestones:

Initial application received (Agency Action)
Completed Date:
Completed application received (Agency Action)
Current Target Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Completed application received (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: http://www.Clenera.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/18/2028

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

Bennett Solar B LLC proposes to construct, operate, maintain, and decommission a 240-megawatt (MW) solar photovoltaic (PV) power generating facility with a 960-MW hour (MWh) battery energy storage system.  The Project area is located approximately 6 miles east of Mountain Home, Idaho, and would be sited on approximately 2,122 acres of public land administered by the U.S. Bureau of Land Management (BLM).  The Project would also include a 230-kilovolt generation interconnection (gen-tie) line, PV module arrays, monitoring and maintenance facilities, electrical collector lines, and access roads.

field_status
System Comments
Agency Milestone Date of 11/17/2025 for Completed application received (Agency Action) has passed by 1 business days
Approver Comments
BLM did not complete the milestone as schedule and did not submit a request to change the milestone date.
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
New Milestone
Completed application received (Agency Action)
Current Target Date:
Response Date
Reporting Agency