Permitting Action Modification History
Modifications on 08/04/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 12-01-2022 | 12-01-2022 | --- | Yes |
| Completed application received (Agency Action) | 11-17-2025 | 11-17-2025 | 06-25-2027 | No |
| Final decision/agency action (Agency Action) | 04-18-2028 | 04-18-2028 | 08-22-2029 | No |
Modifications on 12/11/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 12-01-2022 | 12-01-2022 | --- | Yes |
| Completed application received (Agency Action) | 11-17-2025 | 11-17-2025 | 06-25-2027 | No |
| Final decision/agency action (Agency Action) | 04-18-2028 | 04-18-2028 | 08-22-2029 | No |
Modifications on 02/25/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 12-01-2022 | 12-01-2022 | --- | Yes |
| Completed application received (Agency Action) | 11-17-2025 | 11-17-2025 | --- | No |
| Final decision/agency action (Agency Action) | 04-18-2028 | 04-18-2028 | --- | No |