Permitting Action Modification History

Complete
NMFS completed the milestone earlier than scheduled.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 07-25-2025 07-25-2025 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 08-08-2025 08-11-2025 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 09-08-2025 08-15-2025 --- Yes
In Progress
Project Sponsor submitted the EFH Assessment on 8/8/25.  NOAA determined that the EFH Assessment is complete on 8/11/25. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 07-25-2025 07-25-2025 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 08-08-2025 08-11-2025 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 09-08-2025 09-08-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 07-25-2025 07-25-2025 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 08-08-2025 08-08-2025 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 09-08-2025 09-08-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 07-25-2025 07-25-2025 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 08-08-2025 08-08-2025 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 09-08-2025 09-08-2025 --- No