FAST-41 Missed Date:Environmental Impact Statement (EIS): Scoping (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 06/05/2023 for Scoping (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
Planned
POC Name:
Brian Buttazoni
POC Title:
Planning & Environmental Specialist

Description:

Bonanza Solar, LLC submitted a right-of-way application for the Bonanza Solar Project to the Bureau of Land Management on December 4, 2020. The application indicated that a plan of development, required for right-of-way applications, would be submitted within 60 days of the application filing.  A preliminary plan of development for the Bonanza Solar Project was submitted on March 5, 2021 and an updated version was provided on August 22, 2022.

On April 26, 2023 the BLM determined that it is appropriate to continue processing the right-of-way application, and it will be processed in accordance with the National Environmental Policy Act (NEPA), National Historic Preservation Act (NHPA), Endangered Species Act (ESA), and all other relevant laws, regulations, and policies.

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Current Target Date:
Milestone Details

Public scoping is the first formal public participation opportunity for the Bonanza Solar Project. The 45-day public scoping period was initiated when the Bureau of Land Management (BLM) publishes a Notice of Intent (NOI) in the Federal Register on June 5, 2023. During the scoping period, the BLM will host in-person and virtual workshops. The purpose of scoping is to provide the public with early information on the Applicants' Proposed Action as described in their Preliminary Plan of Development, identify preliminary issues, describe an agency preliminary purpose and need, initial range of alternatives, planning criteria, and information from baseline studies that may have been completed prior to scoping. The scoping period ends on July 20, 2023. After the scoping period, the BLM will publish as scoping report that categorizes the comments that were received.

Scoping (Agency Action)
Current Target Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Scoping (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/07/2026

1 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Bonanza Solar, LLC proposes to construct, operate, and decommission a 300 MW solar photovoltaic and battery energy storage system electrical generation plant and associated facilities on approximately half of the 5,133 acre "application area".  The project proposes to include:

  • A main access road;
  • A secondary access for emergency purposes;
  • A 5.5 mile 230 kV gen-tie;
  • Power blocks of electrical generating capacity;
  • Power collection and power conversion systems;
  • Battery energy storage system;
  • An on-site electrical substation;
  • An on-site operations and maintenance building;
  • Temporary construction laydown areas within the project fence line;
  • A roadway system consisting of internal and perimeter roadways within the project fence line;
  • Microwave/communication tower;
  • Site security, fencing, and lighting; and
  • Meteorological stations.

The proposed project site is entirely on land administered by the Bureau of Land Management, Southern Nevada District. The proposed project would be on Solar Variance lands as identified in the 2012 Final Programmatic Environmental Impact Statement for Solar Energy Development in Six Southwestern States (Solar PEIS).

field_status
System Comments
Agency Milestone Date of 06/05/2023 for Scoping (Agency Action) has passed by 1 business days
Approver Comments
System error
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Scoping (Agency Action)
Current Target Date:
Response Date
Reporting Agency