Permitting Action Modification History

In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 09-06-2024 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 06-05-2025 08-21-2026 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 10-07-2025 11-20-2026 No
In Progress
The FEIS was approved for publishing in the federal register on 8/21/2026. The public comment/review period for the FEIS ends on 9/21/2026. It is estimated that the ROD will be signed following review of the comments, on 10/20/2026., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 09-06-2024 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 06-05-2025 08-21-2026 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 10-07-2025 10-20-2026 No
In Progress
The Draft EIS identified indirect, direct, and cumulative impacts that necessitated communication with cooperating agencies, additional time is needed to further refine and reinforce the design features.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 09-06-2024 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 06-05-2025 12-07-2027 No
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 10-07-2025 04-07-2028 No
In Progress
The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 09-06-2024 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 06-05-2025 07-25-2025 No
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 10-07-2025 --- No
In Progress
On February 11th, EDFR (Project Sponsor) presented a revised site plan that combines elements studied in the Draft EIS to create a project that has fewer environmental impacts. EDFR understands that it will take time to review this revised plan in detail, even though it combines various elements that have already been studied. EDFR has requested extensions of time to allow for the Applicant and the Agencies to coordinate on the incorporation of the revisions and to develop commensurate and appropriate mitigation measures to reflect the reduced impacts of the project. The time will also allow BLM and FWS to incorporate these recent design revisions provided by the Applicant, along with commensurate prudent and reasonable measures, into the Biological Opinion. Subsequently these revisions would be reflected in the Final EIS for the Project. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 09-06-2024 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 06-05-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 10-07-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 09-06-2024 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 04-04-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 08-08-2025 --- No
In Progress
Interagency factors , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 09-06-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 04-04-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 08-08-2025 --- No
In Progress
This project was moved ahead of the previously scheduled dates in the Dashboard. Dates were updated to best available estimates. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 07-05-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 02-05-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 05-16-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- Yes
Scoping (Agency Action) 06-05-2023 06-05-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 10-07-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 06-07-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 10-07-2025 --- No
Planned
The scoping period was moved up as a result of internal project prioritization. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-07-2024 06-05-2023 --- No
Scoping (Agency Action) 06-05-2023 06-05-2023 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 10-07-2024 10-07-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-07-2025 06-07-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-07-2025 10-07-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) --- 03-07-2024 --- No
Scoping (Agency Action) --- --- --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) --- 10-07-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) --- 06-07-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) --- 10-07-2025 --- No